Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
772
matching recommendationsSIC | 232 | Men's And Boys' Furnishings, Work Clothing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
KG0024 # 05 Y:1995 | 05 | 1995 | INSTALL OCCUPANCY SENSORS | $369 | $130 | Not Implemented |
MO0145 # 01 Y:1995 | 01 | 1995 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $26,602 | $779 | Implemented |
MO0145 # 02 Y:1995 | 02 | 1995 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $17,794 | $824 | Not Implemented |
MO0145 # 03 Y:1995 | 03 | 1995 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $1,410 | $40 | Implemented |
MO0145 # 04 Y:1995 | 04 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,037 | $7,975 | Implemented |
MO0145 # 05 Y:1995 | 05 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,293 | $1,629 | Not Implemented |
MO0145 # 06 Y:1995 | 06 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $98 | $165 | Not Implemented |
MO0145 # 07 Y:1995 | 07 | 1995 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,593 | $640 | Implemented |
MO0145 # 08 Y:1995 | 08 | 1995 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,282 | $938 | Implemented |
MO0145 # 09 Y:1995 | 09 | 1995 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $607 | $40 | Implemented |
MO0145 # 10 Y:1995 | 10 | 1995 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $413 | $0 | Implemented |
MO0145 # 11 Y:1995 | 11 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,902 | $14,404 | Implemented |
MO0145 # 12 Y:1995 | 12 | 1995 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $311 | $1,265 | Implemented |
MO0145 # 13 Y:1995 | 13 | 1995 | REPAIR AND ELIMINATE STEAM LEAKS | $838 | $100 | Implemented |
MS0019 # 01 Y:1995 | 01 | 1995 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $5,016 | $10,000 | Not Implemented |
MS0019 # 02 Y:1995 | 02 | 1995 | OPTIMIZE PLANT POWER FACTOR | $5,174 | $3,750 | Implemented |
MS0019 # 03 Y:1995 | 03 | 1995 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,539 | $500 | Implemented |
MS0019 # 04 Y:1995 | 04 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,429 | $1,436 | Implemented |
MS0019 # 05 Y:1995 | 05 | 1995 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,563 | $0 | Not Implemented |
MS0019 # 06 Y:1995 | 06 | 1995 | INSTALL / REPAIR INSULATION ON STEAM LINES | $675 | $1,540 | Not Implemented |
MS0019 # 07 Y:1995 | 07 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $633 | $1,800 | Implemented |
MO0140 # 01 Y:1995 | 01 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,303 | $37,944 | Not Implemented |
MO0140 # 02 Y:1995 | 02 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,214 | $1,488 | Implemented |
MO0140 # 03 Y:1995 | 03 | 1995 | CONVERT COMBUSTION EQUIPMENT TO BURN NATURAL GAS | $3,337 | $200 | Implemented |
MO0140 # 04 Y:1995 | 04 | 1995 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $408 | $150 | Not Implemented |