24
matching recommendationsSIC | 2389 | Apparel And Accessories, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UU0246 # 07 Y:2024 | 07 | 2024 | USE AUTOMATIC FLOW CONTROL | $4,727 | $4,633 | Not Implemented |
UU0246 # 06 Y:2024 | 06 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $8,970 | $42,406 | Implemented |
UU0246 # 05 Y:2024 | 05 | 2024 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $1,731 | $338 | Implemented |
UU0246 # 04 Y:2024 | 04 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $520 | $123 | Implemented |
UU0246 # 03 Y:2024 | 03 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,628 | $3,000 | Implemented |
UU0246 # 02 Y:2024 | 02 | 2024 | OPTIMIZE PLANT POWER FACTOR | $3,514 | $9,000 | Implemented |
UU0246 # 01 Y:2024 | 01 | 2024 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $439 | $900 | Not Implemented |
UU0211 # 02 Y:2023 | 02 | 2023 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $22,030 | $18,300 | Not Implemented |
UU0211 # 06 Y:2023 | 06 | 2023 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $433 | $3,100 | Not Implemented |
UU0211 # 05 Y:2023 | 05 | 2023 | OPTIMIZE PLANT POWER FACTOR | $2,330 | $6,230 | Not Implemented |
UU0211 # 04 Y:2023 | 04 | 2023 | USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS | $3,351 | $26,250 | Implemented |
UU0211 # 03 Y:2023 | 03 | 2023 | DEMOLISH OLD BUILDING TO REDUCE TAX AND INSURANCE BILLS | $7,263 | $12,600 | Not Implemented |
UU0211 # 01 Y:2023 | 01 | 2023 | REPLACE BOILER | $24,600 | $111,300 | Implemented |
UU0171 # 04 Y:2020 | 04 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,725 | $1,500 | Not Implemented |
UU0171 # 03 Y:2020 | 03 | 2020 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $6,190 | $1,100 | Not Implemented |
UU0171 # 02 Y:2020 | 02 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,969 | $4,000 | Implemented |
UU0171 # 01 Y:2020 | 01 | 2020 | ELIMINATE/REDUCE AN OPERATION | $43,211 | $85,000 | Implemented |
UU0015 # 01 Y:2001 | 01 | 2001 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $173 | $141 | Not Implemented |
UU0015 # 07 Y:2001 | 07 | 2001 | IMPROVE COMBUSTION CONTROL CAPABILITY | $12,189 | $21,500 | Not Implemented |
UU0015 # 06 Y:2001 | 06 | 2001 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $839 | $0 | Not Implemented |
UU0015 # 05 Y:2001 | 05 | 2001 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,486 | $5,165 | Not Implemented |
UU0015 # 04 Y:2001 | 04 | 2001 | USE SYNTHETIC LUBRICANT | $1,715 | $800 | Not Implemented |
UU0015 # 03 Y:2001 | 03 | 2001 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,040 | $0 | Not Implemented |
UU0015 # 02 Y:2001 | 02 | 2001 | INSULATE BARE EQUIPMENT | $422 | $625 | Not Implemented |