Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
167
matching recommendationsSIC | 24 | Lumber And Wood Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0161 # 07 Y:1992 | 07 | 1992 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $156 | $1,147 | Not Implemented |
OR0159 # 02 Y:1992 | 02 | 1992 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,001 | $4,750 | Implemented |
OR0159 # 03 Y:1992 | 03 | 1992 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,062 | $4,140 | Implemented |
OR0159 # 04 Y:1992 | 04 | 1992 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $2,364 | $928 | Implemented |
OR0159 # 05 Y:1992 | 05 | 1992 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $499 | $0 | Not Implemented |
OR0159 # 06 Y:1992 | 06 | 1992 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $413 | $1,810 | Not Implemented |
OR0159 # 07 Y:1992 | 07 | 1992 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $10,380 | $9,000 | Implemented |
OR0159 # 01 Y:1992 | 01 | 1992 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,183 | $670 | Implemented |
UD0380 # 01 Y:1992 | 01 | 1992 | USE PLANT OWNED TRANSFORMERS OR LEASE TRANSFORMERS | $37,776 | $0 | Not Implemented |
KU0385 # 01 Y:1992 | 01 | 1992 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,028 | $4,050 | Implemented |
KU0385 # 02 Y:1992 | 02 | 1992 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,119 | $1,080 | Implemented |
KU0385 # 06 Y:1992 | 06 | 1992 | INSTALL TIMERS AND/OR THERMOSTATS | $1,786 | $2,365 | Implemented |
UD0380 # 02 Y:1992 | 02 | 1992 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $3,532 | $3,452 | Implemented |
KU0385 # 05 Y:1992 | 05 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $853 | $0 | Not Implemented |
KU0385 # 04 Y:1992 | 04 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,367 | $5,928 | Not Implemented |
KU0385 # 03 Y:1992 | 03 | 1992 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $440 | $30 | Implemented |
UD0380 # 03 Y:1992 | 03 | 1992 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $4,531 | $0 | Implemented |
UD0380 # 04 Y:1992 | 04 | 1992 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $17,539 | $0 | Not Implemented |
OR0155 # 04 Y:1992 | 04 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,826 | $0 | Implemented |
OR0155 # 02 Y:1992 | 02 | 1992 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $9,144 | $0 | Implemented |
OR0155 # 03 Y:1992 | 03 | 1992 | INSTALL SET-BACK TIMERS | $4,699 | $0 | Implemented |
OR0155 # 05 Y:1992 | 05 | 1992 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,086 | $2,240 | Implemented |
OR0155 # 01 Y:1992 | 01 | 1992 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $62,000 | $1,000 | Implemented |
OR0155 # 06 Y:1992 | 06 | 1992 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,808 | $7,200 | Not Implemented |
OR0154 # 05 Y:1992 | 05 | 1992 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $258 | $0 | Not Implemented |