IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

1,167

matching recommendations
Reset
SIC 24 Lumber And Wood Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OR0091 # 01 Y:1990 01 1990 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $7,456 $3,753 Not Implemented
OR0091 # 02 Y:1990 02 1990 OPTIMIZE PLANT POWER FACTOR $19,523 $21,750 Not Implemented
OR0091 # 03 Y:1990 03 1990 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $9,377 $26,425 Not Implemented
OR0091 # 04 Y:1990 04 1990 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $1,263 $2,745 Not Implemented
OR0096 # 01 Y:1990 01 1990 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $10,821 $5,000 Implemented
OR0096 # 02 Y:1990 02 1990 OPTIMIZE PLANT POWER FACTOR $4,273 $2,500 Implemented
OR0096 # 03 Y:1990 03 1990 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $1,092 $1,530 Implemented
OR0096 # 04 Y:1990 04 1990 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $6,603 $13,000 Implemented
OR0083 # 01 Y:1990 01 1990 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $1,850 $0 Implemented
OR0083 # 02 Y:1990 02 1990 OPTIMIZE PLANT POWER FACTOR $20,444 $16,800 Not Implemented
OR0083 # 03 Y:1990 03 1990 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,646 $5,000 Implemented
OR0083 # 04 Y:1990 04 1990 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $24,439 $46,216 Not Implemented
OR0083 # 05 Y:1990 05 1990 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $190 $490 Not Implemented
OR0078 # 01 Y:1990 01 1990 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $16,426 $0 Implemented
OR0078 # 02 Y:1990 02 1990 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $457 $0 Not Implemented
OR0078 # 03 Y:1990 03 1990 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $8,401 $0 Not Implemented
OR0078 # 04 Y:1990 04 1990 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $14,404 $5,000 Implemented
OR0078 # 05 Y:1990 05 1990 INSTALL SET-BACK TIMERS $12,298 $1,600 Implemented
OR0078 # 06 Y:1990 06 1990 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $9,674 $938 Not Implemented
OR0078 # 07 Y:1990 07 1990 OPTIMIZE PLANT POWER FACTOR $4,077 $0 Not Implemented
OR0071 # 01 Y:1989 01 1989 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $1,915 $500 Not Implemented
OR0071 # 02 Y:1989 02 1989 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $17,682 $5,000 Implemented
OR0071 # 03 Y:1989 03 1989 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $106 $181 Implemented
OR0071 # 04 Y:1989 04 1989 OPTIMIZE PLANT POWER FACTOR $900 $2,250 Not Implemented
OR0071 # 05 Y:1989 05 1989 REDUCE FLUID FLOW RATES $4,615 $12,560 Implemented