Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
224
matching recommendationsSIC | 24 | Lumber And Wood Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
GT0484 # 05 Y:1992 | 05 | 1992 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,360 | $800 | Not Implemented |
GT0484 # 06 Y:1992 | 06 | 1992 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,470 | $150 | Not Implemented |
GT0482 # 01 Y:1992 | 01 | 1992 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $8,400 | $190,520 | Implemented |
GT0482 # 02 Y:1992 | 02 | 1992 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $11,250 | $0 | Implemented |
GT0482 # 03 Y:1992 | 03 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $815 | $2,520 | Implemented |
GT0482 # 04 Y:1992 | 04 | 1992 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,390 | $1,250 | Implemented |
GT0482 # 05 Y:1992 | 05 | 1992 | DISCONNECT BALLASTS | $400 | $0 | Implemented |
GT0482 # 06 Y:1992 | 06 | 1992 | USE FOSSIL FUEL POWERED GENERATOR DURING PEAK DEMAND PERIODS | $141,380 | $750,000 | Implemented |
GT0471 # 01 Y:1992 | 01 | 1992 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $493 | $0 | Not Implemented |
GT0471 # 02 Y:1992 | 02 | 1992 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $253 | $150 | Not Implemented |
GT0471 # 03 Y:1992 | 03 | 1992 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $724 | $200 | Not Implemented |
GT0471 # 04 Y:1992 | 04 | 1992 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $836 | $1,510 | Not Implemented |
GT0471 # 05 Y:1992 | 05 | 1992 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $217 | $10,400 | Not Implemented |
GT0471 # 06 Y:1992 | 06 | 1992 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $149 | $0 | Not Implemented |
GT0471 # 07 Y:1992 | 07 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $750 | $2,210 | Not Implemented |
GT0448 # 01 Y:1991 | 01 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $377 | $120 | Not Implemented |
GT0448 # 02 Y:1991 | 02 | 1991 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $1,180 | $2,870 | Not Implemented |
GT0448 # 03 Y:1991 | 03 | 1991 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $913 | $6,780 | Not Implemented |
GT0448 # 04 Y:1991 | 04 | 1991 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $884 | $100 | Not Implemented |
GT0448 # 05 Y:1991 | 05 | 1991 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $799 | $500 | Not Implemented |
GT0388 # 01 Y:1989 | 01 | 1989 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $3,330 | $3,000 | Not Implemented |
GT0388 # 02 Y:1989 | 02 | 1989 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $5,300 | $10,000 | Not Implemented |
GT0388 # 03 Y:1989 | 03 | 1989 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $278 | $230 | Implemented |
GT0388 # 04 Y:1989 | 04 | 1989 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $626 | $0 | Implemented |
GT0388 # 05 Y:1989 | 05 | 1989 | INSTALL / REPAIR INSULATION ON STEAM LINES | $190 | $410 | Implemented |