Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
195
matching recommendationsSIC | 24 | Lumber And Wood Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0574 # 03 Y:2011 | 03 | 2011 | REDUCE FLUID FLOW RATES | $9,209 | $15,000 | Not Implemented |
OR0574 # 01 Y:2011 | 01 | 2011 | INSTALL OCCUPANCY SENSORS | $35,460 | $21,200 | Not Implemented |
OR0574 # 05 Y:2011 | 05 | 2011 | REDUCE FLUID FLOW RATES | $4,812 | $18,000 | Not Implemented |
OR0574 # 04 Y:2011 | 04 | 2011 | REDUCE FLUID FLOW RATES | $13,265 | $25,000 | Not Implemented |
OR0574 # 02 Y:2011 | 02 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,450 | $7,166 | Implemented |
OR0574 # 06 Y:2011 | 06 | 2011 | FLASH CONDENSATE TO PRODUCE LOWER PRESSURE STEAM | $8,495 | $18,038 | Not Implemented |
OR0573 # 02 Y:2011 | 02 | 2011 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $18,705 | $7,045 | Not Implemented |
OR0573 # 07 Y:2011 | 07 | 2011 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $987 | $4,800 | Not Implemented |
OR0573 # 05 Y:2011 | 05 | 2011 | INSTALL / REPAIR INSULATION ON STEAM LINES | $11,543 | $7,806 | Implemented |
OR0573 # 06 Y:2011 | 06 | 2011 | FLASH CONDENSATE TO PRODUCE LOWER PRESSURE STEAM | $71,712 | $65,575 | Not Implemented |
OR0573 # 03 Y:2011 | 03 | 2011 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $5,064 | $7,045 | Not Implemented |
OR0573 # 04 Y:2011 | 04 | 2011 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $8,821 | $7,045 | Not Implemented |
OR0573 # 01 Y:2011 | 01 | 2011 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $37,057 | $18,500 | Not Implemented |
CO0648 # 02 Y:2011 | 02 | 2011 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,210 | $6,130 | Not Implemented |
CO0648 # 03 Y:2011 | 03 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,780 | $410 | Implemented |
CO0648 # 04 Y:2011 | 04 | 2011 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $270 | $400 | Not Implemented |
CO0648 # 05 Y:2011 | 05 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $600 | $2,710 | Not Implemented |
CO0648 # 01 Y:2011 | 01 | 2011 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $5,240 | $34,900 | Not Implemented |
CO0647 # 01 Y:2011 | 01 | 2011 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,240 | $5,950 | Not Implemented |
CO0647 # 05 Y:2011 | 05 | 2011 | USE SOLAR HEAT TO MAKE ELECTRICTY | $2,420 | $27,500 | Not Implemented |
CO0647 # 04 Y:2011 | 04 | 2011 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $790 | $1,410 | Not Implemented |
CO0647 # 03 Y:2011 | 03 | 2011 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $950 | $600 | Implemented |
CO0647 # 02 Y:2011 | 02 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,490 | $520 | Implemented |
OR0572 # 07 Y:2011 | 07 | 2011 | ESTABLISH BURNER MAINTENANCE SCHEDULE FOR BOILERS | $1,280 | $500 | Implemented |
OR0572 # 06 Y:2011 | 06 | 2011 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $8,030 | $14,750 | Not Implemented |