391
matching recommendationsSIC | 2421 | Sawmills And Planing Mills, General |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0486 # 09 Y:2005 | 09 | 2005 | OPTIMIZE PLANT POWER FACTOR | $3,350 | $3,050 | Implemented |
OR0486 # 08 Y:2005 | 08 | 2005 | REDUCE OR ELIMINATE WASTE | $4,680 | $65 | Not Implemented |
OR0486 # 07 Y:2005 | 07 | 2005 | DEVELOP STANDARD OPERATING PROCEDURES | $5,000 | $40 | Not Implemented |
OR0486 # 06 Y:2005 | 06 | 2005 | RECOVER AND REUSE WASTE MATERIAL | $6,360 | $0 | Not Implemented |
OR0486 # 05 Y:2005 | 05 | 2005 | ADD/MODIFY EQUIPMENT TO IMPROVE DRYING PROCESS | $0 | $6,900 | Implemented |
OR0486 # 04 Y:2005 | 04 | 2005 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $13,000 | $0 | Not Implemented |
OR0486 # 03 Y:2005 | 03 | 2005 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $24,600 | $800 | Not Implemented |
OR0486 # 02 Y:2005 | 02 | 2005 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $75,000 | $50,000 | Implemented |
OR0486 # 01 Y:2005 | 01 | 2005 | MODIFY PROCESS TO REDUCE MATERIAL USE/COST | $536,590 | $3,000 | Not Implemented |
OR0485 # 08 Y:2005 | 08 | 2005 | INSTALL / REPAIR INSULATION ON STEAM LINES | $735 | $2,410 | Not Implemented |
OR0485 # 07 Y:2005 | 07 | 2005 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $64,000 | $134,000 | Not Implemented |
OR0485 # 06 Y:2005 | 06 | 2005 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $12,250 | $0 | Not Implemented |
OR0485 # 05 Y:2005 | 05 | 2005 | OPTIMIZE PLANT POWER FACTOR | $13,480 | $12,250 | Not Implemented |
OR0485 # 04 Y:2005 | 04 | 2005 | USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER | $64,700 | $19,500 | Not Implemented |
OR0485 # 03 Y:2005 | 03 | 2005 | INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN | $6,760 | $15,400 | Not Implemented |
OR0485 # 02 Y:2005 | 02 | 2005 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $19,180 | $0 | Not Implemented |
OR0485 # 01 Y:2005 | 01 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,420 | $6,500 | Not Implemented |
OR0471 # 12 Y:2004 | 12 | 2004 | INCREASE AMOUNT OF CONDENSATE RETURNED | $104,895 | $422,500 | Not Implemented |
OR0471 # 11 Y:2004 | 11 | 2004 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $18,291 | $27,750 | Implemented |
OR0471 # 10 Y:2004 | 10 | 2004 | ADJUST BURNERS FOR EFFICIENT OPERATION | $251,508 | $60,000 | Not Implemented |
OR0471 # 09 Y:2004 | 09 | 2004 | INSTALL SENSORS TO DETECT AND AVOID JAMS | $6,000 | $1,000 | Implemented |
OR0471 # 08 Y:2004 | 08 | 2004 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $6,470 | $9,300 | Not Implemented |
OR0471 # 07 Y:2004 | 07 | 2004 | OPTIMIZE PLANT POWER FACTOR | $18,220 | $20,000 | Not Implemented |
OR0471 # 06 Y:2004 | 06 | 2004 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $44,000 | $92,000 | Not Implemented |
OR0471 # 05 Y:2004 | 05 | 2004 | INSTALL SENSORS TO DETECT AND AVOID JAMS | $102,700 | $77,400 | Not Implemented |