Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
536
matching recommendationsSIC | 2426 | Hardwood Dimension & Flooring Mills |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AR0001 # 04 Y:1993 | 04 | 1993 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $680 | $70 | Implemented |
AR0001 # 05 Y:1993 | 05 | 1993 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $11,028 | $3,400 | Not Implemented |
AR0001 # 06 Y:1993 | 06 | 1993 | USE STEAM PRESSURE REDUCTION TO GENERATE POWER | $33,492 | $25,300 | Implemented |
AR0001 # 07 Y:1993 | 07 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,591 | $227 | Implemented |
OR0146 # 01 Y:1992 | 01 | 1992 | INSTALL SET-BACK TIMERS | $645 | $0 | Not Implemented |
OR0146 # 02 Y:1992 | 02 | 1992 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,041 | $0 | Implemented |
OR0146 # 03 Y:1992 | 03 | 1992 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,813 | $885 | Implemented |
OR0146 # 04 Y:1992 | 04 | 1992 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $440 | $500 | Not Implemented |
OR0146 # 05 Y:1992 | 05 | 1992 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $636 | $1,000 | Implemented |
OR0146 # 06 Y:1992 | 06 | 1992 | INSULATE FEEDWATER TANK | $157 | $333 | Not Implemented |
OR0146 # 07 Y:1992 | 07 | 1992 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,119 | $5,950 | Not Implemented |
OR0146 # 08 Y:1992 | 08 | 1992 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $536 | $8,869 | Implemented |
OR0146 # 09 Y:1992 | 09 | 1992 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $13,355 | $66,726 | Not Implemented |
TN0428 # 01 Y:1991 | 01 | 1991 | REPLACE GASOLINE WITH DIESEL, LPG, OR NATURAL GAS | $217,463 | $0 | Not Implemented |
TN0428 # 02 Y:1991 | 02 | 1991 | INSTALL / REPAIR INSULATION ON STEAM LINES | $361 | $984 | Not Implemented |
TN0428 # 03 Y:1991 | 03 | 1991 | INSTALL SET-BACK TIMERS | $11,136 | $0 | Not Implemented |
TN0428 # 04 Y:1991 | 04 | 1991 | KEEP LAMPS AND REFLECTORS CLEAN | $8,847 | $0 | Not Implemented |
TN0428 # 05 Y:1991 | 05 | 1991 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $73 | $75 | Not Implemented |
TN0428 # 06 Y:1991 | 06 | 1991 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $2,021 | $500 | Not Implemented |
TN0428 # 07 Y:1991 | 07 | 1991 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $742 | $510 | Not Implemented |
TN0428 # 08 Y:1991 | 08 | 1991 | IMPROVE LUBRICATION PRACTICES | $634 | $2,100 | Not Implemented |
TN0428 # 09 Y:1991 | 09 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,578 | $451 | Not Implemented |
TN0428 # 10 Y:1991 | 10 | 1991 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $607 | $660 | Not Implemented |
TN0428 # 11 Y:1991 | 11 | 1991 | OPTIMIZE PLANT POWER FACTOR | $3,912 | $5,900 | Not Implemented |
OR0104 # 01 Y:1990 | 01 | 1990 | OPTIMIZE PLANT POWER FACTOR | $1,124 | $2,400 | Implemented |