Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
20
matching recommendationsSIC | 245 | Wood Buildings And Mobile Homes |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TT0146 # 01 Y:2014 | 01 | 2014 | REPAIR AND ELIMINATE STEAM LEAKS | $1,943 | $822 | Implemented |
TT0137 # 05 Y:2014 | 05 | 2014 | CONVERT COMBUSTION EQUIPMENT TO BURN NATURAL GAS | $26,063 | $4,272 | Implemented |
TT0137 # 03 Y:2014 | 03 | 2014 | INSTALL SKYLIGHTS | $8,488 | $33,000 | Implemented |
TT0137 # 02 Y:2014 | 02 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,154 | $6,230 | Implemented |
TT0137 # 01 Y:2014 | 01 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $10,360 | $822 | Implemented |
TT0109 # 01 Y:2013 | 01 | 2013 | ADJUST BURNERS FOR EFFICIENT OPERATION | $3,611 | $50 | Implemented |
TT0109 # 06 Y:2013 | 06 | 2013 | APPLY FOR INVESTMENT INCENTIVES | $2,271 | $0 | Implemented |
TT0109 # 05 Y:2013 | 05 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,030 | $20,000 | Implemented |
TT0109 # 04 Y:2013 | 04 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,206 | $63 | Implemented |
TT0109 # 03 Y:2013 | 03 | 2013 | UPGRADE CONTROLS ON COMPRESSORS | $7,651 | $25 | Implemented |
TT0045 # 05 Y:2009 | 05 | 2009 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $48,659 | $64,000 | Implemented |
TT0045 # 04 Y:2009 | 04 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,434 | $45,960 | Implemented |
TT0045 # 01 Y:2009 | 01 | 2009 | INSTALL EQUIPMENT TO UTILIZE WASTE FUEL | $100,429 | $34,284 | Implemented |
TN0614 # 04 Y:1997 | 04 | 1997 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $4,875 | $0 | Implemented |
TN0614 # 03 Y:1997 | 03 | 1997 | USE RADIANT HEATER FOR SPOT HEATING | $16,200 | $9,300 | Implemented |
TN0614 # 02 Y:1997 | 02 | 1997 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $24,190 | $41,800 | Implemented |
TN0398 # 01 Y:1990 | 01 | 1990 | INSTALL TIMERS AND/OR THERMOSTATS | $11,814 | $1,500 | Implemented |
TN0398 # 07 Y:1990 | 07 | 1990 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $458 | $380 | Implemented |
TN0398 # 05 Y:1990 | 05 | 1990 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $913 | $0 | Implemented |
TN0398 # 03 Y:1990 | 03 | 1990 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,211 | $870 | Implemented |