Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
418
matching recommendationsSIC | 2493 | Reconstituted Wood Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0718 # 02 Y:2019 | 02 | 2019 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $47,893 | $5,142 | Not Implemented |
OR0718 # 03 Y:2019 | 03 | 2019 | VENTILATION SYSTEM TO SHUT OFF WHEN ROOM IS NOT IN USE | $7,386 | $27,337 | Not Implemented |
OR0718 # 01 Y:2019 | 01 | 2019 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $84,306 | $71,155 | Not Implemented |
NC0624 # 02 Y:2019 | 02 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,403 | $200 | Not Implemented |
NC0624 # 01 Y:2019 | 01 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $37,704 | $24,212 | Not Implemented |
NC0624 # 04 Y:2019 | 04 | 2019 | AVOID REWINDING MOTORS MORE THAN TWICE | $39,622 | $58,313 | Not Implemented |
NC0624 # 03 Y:2019 | 03 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $107 | $450 | Not Implemented |
NC0624 # 05 Y:2019 | 05 | 2019 | REPAIR FURNACES AND OVEN DOORS SO THAT THEY SEAL EFFICIENTLY | $9,555 | $2,000 | Not Implemented |
OK0989 # 04 Y:2018 | 04 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,730 | $13,456 | Implemented |
OK0989 # 03 Y:2018 | 03 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,686 | $6,881 | Implemented |
OK0989 # 02 Y:2018 | 02 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $184,161 | $201,131 | Implemented |
OK0989 # 01 Y:2018 | 01 | 2018 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,205 | $944 | Not Implemented |
OK0989 # 05 Y:2018 | 05 | 2018 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $616 | $5,983 | Not Implemented |
OR0679 # 03 Y:2016 | 03 | 2016 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $10,003 | $10,369 | Not Implemented |
OR0679 # 01 Y:2016 | 01 | 2016 | TURN OFF EQUIPMENT WHEN NOT IN USE | $74,285 | $6,200 | Implemented |
OR0679 # 06 Y:2016 | 06 | 2016 | REPLACE BOILER | $48,912 | $250,000 | Not Implemented |
OR0679 # 05 Y:2016 | 05 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $17,613 | $47,385 | Implemented |
OR0679 # 02 Y:2016 | 02 | 2016 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $20,472 | $0 | Implemented |
OR0679 # 04 Y:2016 | 04 | 2016 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $31,513 | $47,575 | Implemented |
UA0160 # 02 Y:2016 | 02 | 2016 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $85,894 | $0 | Implemented |
UA0160 # 07 Y:2016 | 07 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,220 | $2,995 | Implemented |
UA0160 # 06 Y:2016 | 06 | 2016 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $12,141 | $700 | Not Implemented |
UA0160 # 04 Y:2016 | 04 | 2016 | USE PHOTOCELL CONTROLS | $3,368 | $1,162 | Not Implemented |
UA0160 # 01 Y:2016 | 01 | 2016 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $221,404 | $94,081 | Not Implemented |
UA0160 # 03 Y:2016 | 03 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $83,969 | $169,192 | Not Implemented |