Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,525
matching recommendationsSIC | 25 | Furniture And Fixtures |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IC0093 # 06 Y:2004 | 06 | 2004 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $803 | $300 | Not Implemented |
IC0093 # 07 Y:2004 | 07 | 2004 | UPGRADE OBSOLETE EQUIPMENT | $1,895 | $8,597 | Not Implemented |
LE0202 # 01 Y:2004 | 01 | 2004 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $24,240 | $29,000 | Not Implemented |
LE0202 # 02 Y:2004 | 02 | 2004 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $3,420 | $13,640 | Implemented |
LE0202 # 03 Y:2004 | 03 | 2004 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $1,378 | $2,500 | Implemented |
LE0202 # 04 Y:2004 | 04 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $879 | $0 | Implemented |
LE0202 # 05 Y:2004 | 05 | 2004 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $397 | $500 | Implemented |
LE0202 # 06 Y:2004 | 06 | 2004 | TURN OFF EQUIPMENT WHEN NOT IN USE | $220 | $0 | Implemented |
OK0696 # 01 Y:2004 | 01 | 2004 | INSTALL SET-BACK TIMERS | $19,051 | $4,180 | Implemented |
OK0696 # 02 Y:2004 | 02 | 2004 | RECYCLE AIR FOR HEATING, VENTILATION AND AIR CONDITIONING | $19,260 | $5,950 | Implemented |
OK0696 # 03 Y:2004 | 03 | 2004 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $6,344 | $2,100 | Not Implemented |
OK0696 # 04 Y:2004 | 04 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,308 | $600 | Not Implemented |
OK0696 # 05 Y:2004 | 05 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,876 | $559 | Implemented |
OK0696 # 06 Y:2004 | 06 | 2004 | PAY BILLS ON TIME TO AVOID LATE FEES | $1,545 | $0 | Implemented |
OK0696 # 07 Y:2004 | 07 | 2004 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $700 | $0 | Implemented |
OK0696 # 08 Y:2004 | 08 | 2004 | INSTALL OCCUPANCY SENSORS | $417 | $707 | Implemented |
AS0386 # 01 Y:2004 | 01 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,031 | $120 | Implemented |
AS0386 # 02 Y:2004 | 02 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,011 | $15 | Implemented |
AS0386 # 03 Y:2004 | 03 | 2004 | INSTALL OCCUPANCY SENSORS | $639 | $1,350 | Implemented |
AS0386 # 04 Y:2004 | 04 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $205 | $254 | Not Implemented |
AS0386 # 05 Y:2004 | 05 | 2004 | USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE | $7,680 | $2,000 | Not Implemented |
AS0386 # 06 Y:2004 | 06 | 2004 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $437 | $850 | Not Implemented |
AS0386 # 07 Y:2004 | 07 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,758 | $35,730 | Implemented |
GT0787 # 01 Y:2004 | 01 | 2004 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $20,920 | $13,200 | Implemented |
GT0787 # 02 Y:2004 | 02 | 2004 | INSULATE BARE EQUIPMENT | $1,890 | $800 | Not Implemented |