Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
20
matching recommendationsSIC | 252 | Office Furniture |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SD0620 # 02 Y:2021 | 02 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,133 | $1,050 | Implemented |
SD0620 # 03 Y:2021 | 03 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,884 | $40,350 | Implemented |
SD0620 # 01 Y:2021 | 01 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,249 | $18,262 | Implemented |
SF0521 # 08 Y:2018 | 08 | 2018 | USE SOLAR HEAT TO MAKE ELECTRICTY | $94,006 | $487,058 | Implemented |
SF0521 # 07 Y:2018 | 07 | 2018 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $28,263 | $61,175 | Implemented |
SF0521 # 06 Y:2018 | 06 | 2018 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $23,634 | $44,294 | Implemented |
SF0521 # 05 Y:2018 | 05 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $12,270 | $22,190 | Implemented |
SF0521 # 04 Y:2018 | 04 | 2018 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $2,084 | $2,146 | Implemented |
SF0521 # 03 Y:2018 | 03 | 2018 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,444 | $3,798 | Implemented |
SF0521 # 02 Y:2018 | 02 | 2018 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $130 | $44 | Implemented |
SF0521 # 01 Y:2018 | 01 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,001 | $1,610 | Implemented |
SD0186 # 01 Y:1998 | 01 | 1998 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,357 | $3,530 | Implemented |
SD0186 # 02 Y:1998 | 02 | 1998 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,716 | $0 | Not Implemented |
SD0186 # 03 Y:1998 | 03 | 1998 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $5,665 | $1,180 | Not Implemented |
SD0186 # 04 Y:1998 | 04 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,973 | $500 | Implemented |
SD0186 # 05 Y:1998 | 05 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $928 | $1,853 | Implemented |
SD0186 # 06 Y:1998 | 06 | 1998 | INSTALL SPECTRAL REFLECTORS / DELAMP | $2,785 | $5,115 | Implemented |
SD0186 # 07 Y:1998 | 07 | 1998 | CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS | $64,806 | $732 | Not Implemented |
SD0186 # 08 Y:1998 | 08 | 1998 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $3,050 | $9,000 | Implemented |
SD0186 # 09 Y:1998 | 09 | 1998 | TREAT AND REUSE RINSE WATERS | $512 | $450 | Not Implemented |