Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
236
matching recommendationsSIC | 2522 | Office Furniture, Except Wood |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NC0008 # 01 Y:1993 | 01 | 1993 | RECOVER WASTE HEAT FROM EQUIPMENT | $6,237 | $750 | Not Implemented |
NC0008 # 02 Y:1993 | 02 | 1993 | USE COOLING TOWER WATER INSTEAD OF REFRIGERATION | $3,254 | $3,500 | Not Implemented |
NC0008 # 03 Y:1993 | 03 | 1993 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $5,091 | $13,201 | Implemented |
NC0008 # 04 Y:1993 | 04 | 1993 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,736 | $13,007 | Implemented |
NC0008 # 05 Y:1993 | 05 | 1993 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,196 | $180 | Implemented |
NC0008 # 06 Y:1993 | 06 | 1993 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,395 | $2,500 | Not Implemented |
NC0008 # 07 Y:1993 | 07 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,260 | $12,244 | Implemented |
NC0008 # 08 Y:1993 | 08 | 1993 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,691 | $150 | Implemented |
NC0008 # 09 Y:1993 | 09 | 1993 | RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR | $347 | $330 | Not Implemented |
IA0051 # 01 Y:1993 | 01 | 1993 | RECOVER WASTE HEAT FROM EQUIPMENT | $70,781 | $20,361 | Not Implemented |
IA0051 # 02 Y:1993 | 02 | 1993 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $324 | $261 | Implemented |
IA0051 # 03 Y:1993 | 03 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,778 | $2,511 | Implemented |
IA0051 # 04 Y:1993 | 04 | 1993 | INSTALL SET-BACK TIMERS | $10,125 | $0 | Implemented |
IA0051 # 05 Y:1993 | 05 | 1993 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $2,435 | $170 | Not Implemented |
IA0051 # 06 Y:1993 | 06 | 1993 | INSTALL OCCUPANCY SENSORS | $1,750 | $1,890 | Implemented |
IA0051 # 07 Y:1993 | 07 | 1993 | RECOVER WASTE HEAT FROM EQUIPMENT | $6,297 | $810 | Not Implemented |
IA0051 # 08 Y:1993 | 08 | 1993 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,028 | $320 | Implemented |
IA0051 # 09 Y:1993 | 09 | 1993 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $188 | $20 | Implemented |
AM0148 # 01 Y:1992 | 01 | 1992 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $1,800 | $400 | Implemented |
AM0148 # 02 Y:1992 | 02 | 1992 | INSULATE BARE EQUIPMENT | $1,275 | $1,275 | Implemented |
AM0148 # 03 Y:1992 | 03 | 1992 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $496 | $420 | Implemented |
AM0148 # 04 Y:1992 | 04 | 1992 | INSTALL SET-BACK TIMERS | $354 | $350 | Implemented |
AM0148 # 05 Y:1992 | 05 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $130 | $0 | Implemented |
AM0148 # 06 Y:1992 | 06 | 1992 | INSULATE BARE EQUIPMENT | $140 | $200 | Not Implemented |
WI0058 # 01 Y:1989 | 01 | 1989 | INSTALL TIMERS AND/OR THERMOSTATS | $20,838 | $3,000 | Implemented |