Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
273
matching recommendationsSIC | 259 | Miscellaneous Furniture And Fixtures |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0559 # 02 Y:2020 | 02 | 2020 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $19,566 | $32,210 | Implemented |
UF0559 # 03 Y:2020 | 03 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,767 | $956 | Implemented |
UF0559 # 04 Y:2020 | 04 | 2020 | REPOSITION OVEN WALLS TO REDUCE HEATED SPACE | $3,003 | $750 | Implemented |
UD0919 # 12 Y:2015 | 12 | 2015 | MAKE A NEW BY-PRODUCT | $24,789 | $46,000 | Not Implemented |
UD0919 # 10 Y:2015 | 10 | 2015 | USE WASTE HEAT FROM FLUE GASES TO HEAT SPACE CONDITIONING AIR | $2,652 | $5,000 | Not Implemented |
UD0919 # 09 Y:2015 | 09 | 2015 | INSTALL MOTOR VOLTAGE CONTROLLER ON LIGHTLY LOADED MOTORS | $4,591 | $4,300 | Not Implemented |
UD0919 # 05 Y:2015 | 05 | 2015 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $36,602 | $22,000 | Not Implemented |
UD0919 # 02 Y:2015 | 02 | 2015 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $9,792 | $0 | Implemented |
UD0919 # 13 Y:2015 | 13 | 2015 | CLEAN FOULING FROM WATER LINES REGULARLY | $5,080 | $2,750 | Not Implemented |
UD0919 # 07 Y:2015 | 07 | 2015 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $11,674 | $0 | Implemented |
UD0919 # 06 Y:2015 | 06 | 2015 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,496 | $2,295 | Not Implemented |
UD0919 # 03 Y:2015 | 03 | 2015 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $1,936 | $50 | Implemented |
UD0919 # 08 Y:2015 | 08 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,715 | $0 | Implemented |
UD0919 # 11 Y:2015 | 11 | 2015 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $242 | $700 | Not Implemented |
UD0919 # 04 Y:2015 | 04 | 2015 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $29,266 | $9,200 | Implemented |
UD0919 # 01 Y:2015 | 01 | 2015 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,757 | $0 | Implemented |
IP0008 # 01 Y:2013 | 01 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $16,340 | $0 | Implemented |
IP0008 # 02 Y:2013 | 02 | 2013 | UPGRADE CONTROLS ON COMPRESSORS | $3,853 | $0 | Implemented |
IP0008 # 07 Y:2013 | 07 | 2013 | INSTALL OCCUPANCY SENSORS | $282 | $107 | Not Implemented |
IP0008 # 04 Y:2013 | 04 | 2013 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,234 | $0 | Implemented |
IP0008 # 09 Y:2013 | 09 | 2013 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $7,093 | $15,665 | Not Implemented |
IP0008 # 05 Y:2013 | 05 | 2013 | INSULATE BARE EQUIPMENT | $5,583 | $900 | Not Implemented |
IP0008 # 06 Y:2013 | 06 | 2013 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,117 | $449 | Not Implemented |
IP0008 # 08 Y:2013 | 08 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,510 | $9,972 | Implemented |
IP0008 # 03 Y:2013 | 03 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,703 | $0 | Implemented |