IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

41

matching recommendations
Reset
SIC 26 Paper And Allied Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
IP0162 # 07 Y:2022 07 2022 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $923 $2,186 Implemented
IP0162 # 04 Y:2022 04 2022 INSTALL OCCUPANCY SENSORS $377 $137 Implemented
IP0162 # 03 Y:2022 03 2022 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $634 $152 Implemented
IP0162 # 02 Y:2022 02 2022 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $8,724 $1,255 Implemented
IP0162 # 01 Y:2022 01 2022 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA $1,109 $12 Implemented
IP0162 # 05 Y:2022 05 2022 USE "HEAT WHEEL" OR OTHER HEAT EXCHANGER TO CROSS-EXCHANGE BUILDING EXHAUST AIR WITH MAKE-UP AIR $45,478 $37,072 Implemented
IP0070 # 02 Y:2016 02 2016 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $8,543 $74 Implemented
IP0070 # 03 Y:2016 03 2016 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,137 $40 Implemented
IP0070 # 04 Y:2016 04 2016 INSTALL OCCUPANCY SENSORS $996 $113 Implemented
IP0056 # 02 Y:2016 02 2016 PAY BILLS ON TIME TO AVOID LATE FEES $1,368 $0 Implemented
IP0056 # 03 Y:2016 03 2016 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA $1,361 $0 Implemented
IP0056 # 04 Y:2016 04 2016 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $9,759 $165 Implemented
IP0056 # 05 Y:2016 05 2016 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $5,870 $300 Implemented
IP0056 # 10 Y:2016 10 2016 INSTALL OCCUPANCY SENSORS $311 $218 Implemented
IP0019 # 06 Y:2013 06 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,889 $3,258 Implemented
IP0019 # 04 Y:2013 04 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $13,885 $164 Implemented
IP0019 # 03 Y:2013 03 2013 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $493 $0 Implemented
IP0018 # 05 Y:2013 05 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $7,545 $1,400 Implemented
IP0018 # 07 Y:2013 07 2013 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $99,761 $59,384 Implemented
IP0018 # 02 Y:2013 02 2013 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $109,212 $0 Implemented
UL0168 # 02 Y:1996 02 1996 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $960 $40 Implemented
UL0168 # 08 Y:1996 08 1996 USE EVAPORATION TO CONCENTRATE MATERIAL $16,800 $5,070 Implemented
UL0168 # 01 Y:1996 01 1996 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $14,936 $1,400 Implemented
UL0168 # 03 Y:1996 03 1996 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $4,464 $35 Implemented
ND0235 # 07 Y:1995 07 1995 MINIMIZE CONTAMINATION OF WATER BEFORE TREATMENT $15,000 $30,000 Implemented