Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
70
matching recommendationsSIC | 26 | Paper And Allied Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LT0029 # 01 Y:1985 | 01 | 1985 | INSTALL / REPAIR INSULATION ON STEAM LINES | $170 | $111 | Implemented |
LT0029 # 03 Y:1985 | 03 | 1985 | INSTALL TIMERS AND/OR THERMOSTATS | $2,230 | $450 | Implemented |
LT0029 # 04 Y:1985 | 04 | 1985 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $713 | $150 | Implemented |
AT0023 # 06 Y:1985 | 06 | 1985 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $3,785 | $2,700 | Implemented |
AT0022 # 03 Y:1985 | 03 | 1985 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $394 | $0 | Implemented |
AT0022 # 04 Y:1985 | 04 | 1985 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $272 | $250 | Implemented |
AT0022 # 05 Y:1985 | 05 | 1985 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $830 | $450 | Implemented |
AT0022 # 01 Y:1985 | 01 | 1985 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $449 | $422 | Implemented |
AT0022 # 02 Y:1985 | 02 | 1985 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $17,673 | $300 | Implemented |
AT0022 # 07 Y:1985 | 07 | 1985 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,564 | $205 | Implemented |
AT0022 # 06 Y:1985 | 06 | 1985 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $2,293 | $1,920 | Implemented |
AT0023 # 04 Y:1985 | 04 | 1985 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $156 | $250 | Implemented |
KU0170 # 17 Y:1985 | 17 | 1985 | TURN OFF EQUIPMENT WHEN NOT IN USE | $551 | $0 | Implemented |
OK0182 # 01 Y:1985 | 01 | 1985 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $225 | $310 | Implemented |
OK0182 # 05 Y:1985 | 05 | 1985 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $680 | $325 | Implemented |
KU0170 # 02 Y:1985 | 02 | 1985 | INSTALL TIMERS AND/OR THERMOSTATS | $29,255 | $18 | Implemented |
KU0170 # 03 Y:1985 | 03 | 1985 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,755 | $2,656 | Implemented |
KU0170 # 04 Y:1985 | 04 | 1985 | REPAIR AND ELIMINATE STEAM LEAKS | $5,297 | $300 | Implemented |
KU0170 # 05 Y:1985 | 05 | 1985 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $4,901 | $6,000 | Implemented |
KU0170 # 14 Y:1985 | 14 | 1985 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $1,514 | $1,300 | Implemented |
KU0170 # 11 Y:1985 | 11 | 1985 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $147 | $20 | Implemented |
KU0170 # 10 Y:1985 | 10 | 1985 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $606 | $300 | Implemented |
KU0170 # 09 Y:1985 | 09 | 1985 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $735 | $30 | Implemented |
KU0170 # 08 Y:1985 | 08 | 1985 | USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS | $2,764 | $700 | Implemented |
KU0170 # 06 Y:1985 | 06 | 1985 | INCREASE AMOUNT OF CONDENSATE RETURNED | $1,746 | $1,000 | Implemented |