Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
200
matching recommendationsSIC | 26 | Paper And Allied Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
GT0961 # 01 Y:2023 | 01 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $58,279 | $1,850 | Implemented |
GT0961 # 05 Y:2023 | 05 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,590 | $25,886 | Implemented |
GT0961 # 04 Y:2023 | 04 | 2023 | INSTALL OCCUPANCY SENSORS | $4,776 | $4,480 | Implemented |
GT0961 # 02 Y:2023 | 02 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $8,116 | $800 | Implemented |
GT0961 # 03 Y:2023 | 03 | 2023 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $1,851 | $900 | Implemented |
GT0961 # 06 Y:2023 | 06 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $850,335 | $9,659,438 | Not Implemented |
GT0886 # 05 Y:2011 | 05 | 2011 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $24,782 | $14,000 | Implemented |
GT0886 # 03 Y:2011 | 03 | 2011 | DEVELOP A REPAIR/REPLACE POLICY | $3,617 | $9,994 | Implemented |
GT0886 # 02 Y:2011 | 02 | 2011 | METER WASTE WATER | $5,529 | $2,500 | Implemented |
GT0886 # 01 Y:2011 | 01 | 2011 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $30,160 | $2,400 | Not Implemented |
GT0886 # 04 Y:2011 | 04 | 2011 | UPGRADE CONTROLS ON COMPRESSORS | $51,129 | $25,000 | Implemented |
GT0849 # 04 Y:2008 | 04 | 2008 | INCREASE AMOUNT OF CONDENSATE RETURNED | $292,310 | $18,200 | Implemented |
GT0849 # 06 Y:2008 | 06 | 2008 | USE WASTE HEAT TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR | $228,740 | $900,000 | Not Implemented |
GT0849 # 03 Y:2008 | 03 | 2008 | REDUCE EXCESSIVE BOILER BLOWDOWN | $57,260 | $0 | Not Implemented |
GT0849 # 01 Y:2008 | 01 | 2008 | BURN A LESS EXPENSIVE GRADE OF FUEL | $98,980 | $0 | Not Implemented |
GT0849 # 05 Y:2008 | 05 | 2008 | INSTALL / REPAIR INSULATION ON STEAM LINES | $35,083 | $40,800 | Not Implemented |
GT0849 # 02 Y:2008 | 02 | 2008 | BURN WOOD BY-PRODUCTS FOR HEAT | $175,600 | $100,000 | Not Implemented |
GT0840 # 04 Y:2007 | 04 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $515 | $2,301 | Implemented |
GT0840 # 06 Y:2007 | 06 | 2007 | RECOVER WASTE HEAT FROM EQUIPMENT | $830 | $2,500 | Not Implemented |
GT0840 # 01 Y:2007 | 01 | 2007 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $8,598 | $30,000 | Not Implemented |
GT0840 # 02 Y:2007 | 02 | 2007 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,574 | $0 | Not Implemented |
GT0840 # 05 Y:2007 | 05 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,943 | $3,750 | Implemented |
GT0840 # 03 Y:2007 | 03 | 2007 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $4,377 | $14,862 | Implemented |
GT0836 # 08 Y:2007 | 08 | 2007 | INSTALL OCCUPANCY SENSORS | $11,122 | $22,750 | Not Implemented |
GT0836 # 01 Y:2007 | 01 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $48,543 | $3,750 | Implemented |