Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
348
matching recommendationsSIC | 26 | Paper And Allied Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD1025 # 03 Y:2020 | 03 | 2020 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,411 | $4,000 | Not Implemented |
UD1025 # 08 Y:2020 | 08 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $27,963 | $26,366 | Not Implemented |
UD1025 # 09 Y:2020 | 09 | 2020 | INSTALL OCCUPANCY SENSORS | $11,875 | $4,845 | Not Implemented |
UD1025 # 05 Y:2020 | 05 | 2020 | REDUCE EXCESSIVE BOILER BLOWDOWN | $6,710 | $5,224 | Not Implemented |
UD1025 # 06 Y:2020 | 06 | 2020 | COMBINE UTILITY METERS | $8,278 | $0 | Not Implemented |
UD1025 # 01 Y:2020 | 01 | 2020 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $2,747 | $0 | Not Implemented |
UD1025 # 07 Y:2020 | 07 | 2020 | OPTIMIZE PLANT POWER FACTOR | $3,612 | $7,325 | Not Implemented |
UD1025 # 10 Y:2020 | 10 | 2020 | INSTALL EQUIPMENT TO MOVE PRODUCT | $454,408 | $375,000 | Not Implemented |
UD1025 # 04 Y:2020 | 04 | 2020 | INSULATE BARE EQUIPMENT | $83,809 | $25,133 | Not Implemented |
UD1025 # 02 Y:2020 | 02 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $16,051 | $340 | Implemented |
UD0964 # 03 Y:2017 | 03 | 2017 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $5,847 | $500 | Not Implemented |
UD0964 # 08 Y:2017 | 08 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,225 | $21,449 | Not Implemented |
UD0964 # 09 Y:2017 | 09 | 2017 | INSTALL SPECTRAL REFLECTORS / DELAMP | $6,075 | $0 | Not Implemented |
UD0964 # 07 Y:2017 | 07 | 2017 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $31,348 | $36,424 | Not Implemented |
UD0964 # 02 Y:2017 | 02 | 2017 | USE OPTIMUM TEMPERATURE | $652 | $500 | Not Implemented |
UD0964 # 05 Y:2017 | 05 | 2017 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $4,749 | $2,840 | Not Implemented |
UD0964 # 04 Y:2017 | 04 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $10,000 | $1,000 | Not Implemented |
UD0964 # 01 Y:2017 | 01 | 2017 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $6,083 | $0 | Not Implemented |
UD0964 # 06 Y:2017 | 06 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,522 | $0 | Not Implemented |
UD0950 # 10 Y:2016 | 10 | 2016 | DEVELOP A REPAIR/REPLACE POLICY | $240 | $460 | Implemented |
UD0950 # 08 Y:2016 | 08 | 2016 | INSTALL OCCUPANCY SENSORS | $4,004 | $1,452 | Not Implemented |
UD0950 # 13 Y:2016 | 13 | 2016 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $7,880 | $0 | Implemented |
UD0950 # 12 Y:2016 | 12 | 2016 | OPTIMIZE PLANT POWER FACTOR | $1,295 | $6,540 | Not Implemented |
UD0950 # 11 Y:2016 | 11 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $335 | $1,000 | Implemented |
UD0950 # 09 Y:2016 | 09 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,530 | $4,047 | Not Implemented |