Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
122
matching recommendationsSIC | 26 | Paper And Allied Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MA0158 # 04 Y:1989 | 04 | 1989 | INSULATE BARE EQUIPMENT | $3,704 | $4,682 | Not Implemented |
MA0158 # 05 Y:1989 | 05 | 1989 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $600 | $2,000 | Not Implemented |
MA0125 # 01 Y:1988 | 01 | 1988 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,470 | $0 | Not Implemented |
MA0125 # 02 Y:1988 | 02 | 1988 | INSULATE BARE EQUIPMENT | $2,156 | $1,143 | Not Implemented |
MA0125 # 03 Y:1988 | 03 | 1988 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $985 | $201 | Implemented |
MA0125 # 04 Y:1988 | 04 | 1988 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $17,614 | $18,000 | Not Implemented |
MA0118 # 01 Y:1988 | 01 | 1988 | INSULATE BARE EQUIPMENT | $4,171 | $1,275 | Not Implemented |
MA0118 # 02 Y:1988 | 02 | 1988 | REPAIR OR REPLACE STEAM TRAPS | $8,138 | $1,464 | Implemented |
MA0118 # 03 Y:1988 | 03 | 1988 | INSTALL / REPAIR INSULATION ON STEAM LINES | $2,626 | $930 | Implemented |
MA0118 # 04 Y:1988 | 04 | 1988 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $743 | $990 | Implemented |
MA0118 # 05 Y:1988 | 05 | 1988 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $63,601 | $46,000 | Not Implemented |
MA0118 # 06 Y:1988 | 06 | 1988 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $2,658 | $377 | Implemented |
MA0118 # 07 Y:1988 | 07 | 1988 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $2,200 | $340 | Not Implemented |
MA0118 # 08 Y:1988 | 08 | 1988 | USE COMBINED CYCLE GAS TURBINE GENERATOR SETS WITH WASTE HEAT BOILERS CONNECTED TO TURBINE EXHAUST | $371,179 | $670,000 | Not Implemented |
MA0118 # 09 Y:1988 | 09 | 1988 | USE OPTIMUM THICKNESS INSULATION | $2,742 | $2,160 | Implemented |
MA0118 # 10 Y:1988 | 10 | 1988 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $14,763 | $20,100 | Not Implemented |
MA0029 # 01 Y:1985 | 01 | 1985 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $344 | $94 | Not Implemented |
MA0029 # 02 Y:1985 | 02 | 1985 | USE DIRECT AIR SUPPLY TO EXHAUST HOODS | $17,454 | $9,015 | Not Implemented |
MA0029 # 03 Y:1985 | 03 | 1985 | RECOVER WASTE HEAT FROM EQUIPMENT | $6,980 | $268 | Not Implemented |
MA0029 # 04 Y:1985 | 04 | 1985 | MINIMIZE OPERATION OF EQUIPMENT MAINTAINED IN STANDBY CONDITION | $636 | $763 | Not Implemented |
MA0029 # 05 Y:1985 | 05 | 1985 | REDUCE FLUID FLOW RATES | $2,655 | $0 | Not Implemented |
MA0029 # 06 Y:1985 | 06 | 1985 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $5,968 | $2,000 | Not Implemented |