Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
33
matching recommendationsSIC | 2621 | Paper Mills |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
BD0006 # 02 Y:1994 | 02 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,453 | $9,831 | Implemented |
BD0006 # 03 Y:1994 | 03 | 1994 | INSTALL OCCUPANCY SENSORS | $2,909 | $150 | Implemented |
BD0006 # 04 Y:1994 | 04 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $12,040 | $27,720 | Implemented |
BD0006 # 01 Y:1994 | 01 | 1994 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $68,353 | $250 | Not Implemented |
MA0304 # 01 Y:1994 | 01 | 1994 | USE SYNTHETIC LUBRICANT | $30,227 | $8,568 | Implemented |
MA0304 # 02 Y:1994 | 02 | 1994 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $37,969 | $30,800 | Implemented |
MA0304 # 03 Y:1994 | 03 | 1994 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $12,749 | $0 | Implemented |
MA0304 # 04 Y:1994 | 04 | 1994 | SHADE WINDOWS FROM SUMMER SUN | $1,847 | $5,000 | Implemented |
GT0520 # 06 Y:1994 | 06 | 1994 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $20,350 | $0 | Implemented |
GT0520 # 07 Y:1994 | 07 | 1994 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $81,750 | $124,600 | Not Implemented |
GT0520 # 05 Y:1994 | 05 | 1994 | USE MINIMUM STEAM OPERATING PRESSURE | $2,350 | $0 | Not Implemented |
GT0520 # 04 Y:1994 | 04 | 1994 | REPAIR AND ELIMINATE STEAM LEAKS | $3,845 | $500 | Implemented |
GT0520 # 03 Y:1994 | 03 | 1994 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $9,900 | $450 | Implemented |
GT0520 # 02 Y:1994 | 02 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $460 | $835 | Implemented |
GT0520 # 01 Y:1994 | 01 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,300 | $9,420 | Implemented |
MA0299 # 06 Y:1994 | 06 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $597 | $525 | Not Implemented |
MA0299 # 11 Y:1994 | 11 | 1994 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $413 | $1,650 | Not Implemented |
MA0299 # 10 Y:1994 | 10 | 1994 | REPAIR OR REPLACE STEAM TRAPS | $470 | $1,396 | Not Implemented |
MA0299 # 09 Y:1994 | 09 | 1994 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $1,660 | $5,030 | Not Implemented |
MA0299 # 08 Y:1994 | 08 | 1994 | INSULATE BARE EQUIPMENT | $4,792 | $1,267 | Not Implemented |
MA0299 # 07 Y:1994 | 07 | 1994 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $6,724 | $0 | Not Implemented |
MA0299 # 05 Y:1994 | 05 | 1994 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $1,707 | $0 | Not Implemented |
MA0299 # 04 Y:1994 | 04 | 1994 | DISCONNECT BALLASTS | $8,033 | $411 | Not Implemented |
MA0299 # 03 Y:1994 | 03 | 1994 | TURN OFF EQUIPMENT WHEN NOT IN USE | $9,593 | $1,526 | Not Implemented |
MA0299 # 02 Y:1994 | 02 | 1994 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $4,797 | $4,000 | Not Implemented |