Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
380
matching recommendationsSIC | 2631 | Paperboard Mills |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0401 # 09 Y:2010 | 09 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,622 | $312 | Implemented |
WV0401 # 06 Y:2010 | 06 | 2010 | RECYCLE AIR FOR HEATING, VENTILATION AND AIR CONDITIONING | $11,226 | $20,400 | Implemented |
WV0401 # 07 Y:2010 | 07 | 2010 | INSTALL DRY SPRINKLER SYSTEM OR OTHER METHOD TO REDUCE HEATING REQUIREMENTS | $7,432 | $16,240 | Not Implemented |
WV0401 # 08 Y:2010 | 08 | 2010 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $6,432 | $2,028 | Implemented |
WV0396 # 11 Y:2009 | 11 | 2009 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,630 | $445 | Not Implemented |
WV0396 # 09 Y:2009 | 09 | 2009 | OPTIMIZE PLANT POWER FACTOR | $7,614 | $28,000 | Not Implemented |
WV0396 # 14 Y:2009 | 14 | 2009 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $781 | $575 | Implemented |
WV0396 # 13 Y:2009 | 13 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $829 | $0 | Implemented |
WV0396 # 12 Y:2009 | 12 | 2009 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $846 | $50 | Implemented |
WV0396 # 10 Y:2009 | 10 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,796 | $263 | Implemented |
WV0396 # 01 Y:2009 | 01 | 2009 | PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST | $404,150 | $744,800 | Not Implemented |
WV0396 # 02 Y:2009 | 02 | 2009 | USE MINIMUM STEAM OPERATING PRESSURE | $80,973 | $54,000 | Not Implemented |
WV0396 # 03 Y:2009 | 03 | 2009 | USE STEAM PRESSURE REDUCTION TO GENERATE POWER | $72,044 | $295,680 | Not Implemented |
WV0396 # 04 Y:2009 | 04 | 2009 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $69,637 | $1,000 | Implemented |
WV0396 # 05 Y:2009 | 05 | 2009 | INSTALL / REPAIR INSULATION ON STEAM LINES | $10,128 | $3,390 | Implemented |
WV0396 # 06 Y:2009 | 06 | 2009 | DEVELOP A REPAIR/REPLACE POLICY | $9,954 | $1,094 | Implemented |
WV0396 # 07 Y:2009 | 07 | 2009 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $9,556 | $10,996 | Not Implemented |
WV0396 # 08 Y:2009 | 08 | 2009 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $8,609 | $1,000 | Implemented |
UM0341 # 07 Y:2008 | 07 | 2008 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,356 | $515 | Not Implemented |
UM0341 # 06 Y:2008 | 06 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,111 | $8,160 | Not Implemented |
UM0341 # 05 Y:2008 | 05 | 2008 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $8,572 | $5,000 | Not Implemented |
UM0341 # 04 Y:2008 | 04 | 2008 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $13,835 | $4,800 | Not Implemented |
UM0341 # 03 Y:2008 | 03 | 2008 | RECOVER WASTE HEAT FROM EQUIPMENT | $31,965 | $59,142 | Not Implemented |
UM0341 # 02 Y:2008 | 02 | 2008 | INSULATE BARE EQUIPMENT | $79,804 | $53,414 | Implemented |
UM0341 # 01 Y:2008 | 01 | 2008 | INSULATE BARE EQUIPMENT | $101,548 | $18,088 | Not Implemented |