IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

136

matching recommendations
Reset
SIC 265 Paperboard Containers And Boxes
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UD0787 # 08 Y:2008 08 2008 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,656 $0 Not Implemented
UD0787 # 02 Y:2008 02 2008 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $35,242 $107,122 Implemented
UD0787 # 06 Y:2008 06 2008 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) $2,330 $300 Not Implemented
UD0787 # 05 Y:2008 05 2008 OPTIMIZE PLANT POWER FACTOR $7,098 $39,000 Not Implemented
UD0787 # 07 Y:2008 07 2008 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,714 $2,828 Not Implemented
UD0787 # 04 Y:2008 04 2008 INSTALL / REPAIR INSULATION ON STEAM LINES $9,025 $2,424 Implemented
UD0787 # 10 Y:2008 10 2008 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $388 $1,000 Implemented
UD0787 # 01 Y:2008 01 2008 REDUCE VENTILATION AIR $47,843 $62,700 Implemented
UD0787 # 09 Y:2008 09 2008 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,351 $1,000 Implemented
UD0787 # 03 Y:2008 03 2008 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $12,341 $6,560 Not Implemented
UD0641 # 01 Y:2002 01 2002 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS $72,243 $0 Not Implemented
UD0641 # 03 Y:2002 03 2002 USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION $28,507 $400 Implemented
UD0641 # 14 Y:2002 14 2002 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $1,060 $0 Not Implemented
UD0641 # 04 Y:2002 04 2002 RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR $17,780 $20,000 Not Implemented
UD0641 # 06 Y:2002 06 2002 USE RADIANT HEATER FOR SPOT HEATING $15,849 $22,500 Not Implemented
UD0641 # 07 Y:2002 07 2002 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $10,676 $22,800 Implemented
UD0641 # 02 Y:2002 02 2002 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $31,699 $37,000 Not Implemented
UD0641 # 15 Y:2002 15 2002 SWITCH TO A SOLVENT THAT CAN BE CLEANED AND RE-USED $673 $1,275 Not Implemented
UD0641 # 05 Y:2002 05 2002 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $16,888 $59,307 Not Implemented
UD0641 # 10 Y:2002 10 2002 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $2,588 $2,500 Implemented
UD0641 # 09 Y:2002 09 2002 DISCONNECT BALLASTS $2,709 $1,968 Not Implemented
UD0641 # 11 Y:2002 11 2002 INSTALL OCCUPANCY SENSORS $2,180 $121 Not Implemented
UD0641 # 08 Y:2002 08 2002 REPROCESS SPENT OILS ON SITE FOR RE-USE $3,403 $3,400 Not Implemented
UD0641 # 12 Y:2002 12 2002 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,957 $9,969 Implemented
UD0641 # 13 Y:2002 13 2002 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING $1,451 $5,000 Not Implemented