Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,551
matching recommendationsSIC | 265 | Paperboard Containers And Boxes |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WI0139 # 01 Y:1992 | 01 | 1992 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $23,212 | $500 | Not Implemented |
WI0139 # 02 Y:1992 | 02 | 1992 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $14,993 | $30,000 | Not Implemented |
WI0139 # 03 Y:1992 | 03 | 1992 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $13,842 | $0 | Not Implemented |
WI0139 # 04 Y:1992 | 04 | 1992 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,837 | $5,451 | Not Implemented |
WI0139 # 05 Y:1992 | 05 | 1992 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $619 | $0 | Not Implemented |
WI0139 # 06 Y:1992 | 06 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,205 | $5,344 | Implemented |
WI0139 # 07 Y:1992 | 07 | 1992 | INSTALL SET-BACK TIMERS | $128 | $200 | Not Implemented |
WI0139 # 08 Y:1992 | 08 | 1992 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $2,876 | $0 | Not Implemented |
WI0139 # 09 Y:1992 | 09 | 1992 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $69 | $0 | Not Implemented |
WI0139 # 10 Y:1992 | 10 | 1992 | INSTALL TIMERS AND/OR THERMOSTATS | $1,790 | $800 | Not Implemented |
WI0139 # 11 Y:1992 | 11 | 1992 | INSTALL AUTOMATIC STACK DAMPER | $847 | $1,400 | Not Implemented |
WI0139 # 12 Y:1992 | 12 | 1992 | SHUT OFF PILOTS IN STANDBY EQUIPMENT | $190 | $0 | Not Implemented |
WI0139 # 13 Y:1992 | 13 | 1992 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,692 | $2,000 | Not Implemented |
WI0139 # 14 Y:1992 | 14 | 1992 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $913 | $650 | Implemented |
WI0139 # 15 Y:1992 | 15 | 1992 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $685 | $740 | Not Implemented |
HO0011 # 01 Y:1992 | 01 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,962 | $5,609 | Implemented |
HO0011 # 02 Y:1992 | 02 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,300 | $4,500 | Implemented |
HO0011 # 03 Y:1992 | 03 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,264 | $14,884 | Implemented |
HO0011 # 04 Y:1992 | 04 | 1992 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $4,695 | $0 | Not Implemented |
HO0011 # 05 Y:1992 | 05 | 1992 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $216 | $186 | Not Implemented |
IA0011 # 01 Y:1991 | 01 | 1991 | INSTALL DE-AERATOR IN PLACE OF CONDENSATE TANK | $57,580 | $70,000 | Not Implemented |
IA0011 # 02 Y:1991 | 02 | 1991 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $887 | $1,592 | Not Implemented |
IA0011 # 03 Y:1991 | 03 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $727 | $0 | Not Implemented |
IA0011 # 04 Y:1991 | 04 | 1991 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $622 | $0 | Not Implemented |
ND0015 # 01 Y:1991 | 01 | 1991 | REDUCE VENTILATION AIR | $1,838 | $750 | Implemented |