Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,551
matching recommendationsSIC | 265 | Paperboard Containers And Boxes |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IA0286 # 09 Y:2002 | 09 | 2002 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $2,570 | $3,500 | Not Implemented |
IA0286 # 10 Y:2002 | 10 | 2002 | RECOVER WASTE HEAT FROM EQUIPMENT | $6,028 | $2,680 | Not Implemented |
IA0286 # 11 Y:2002 | 11 | 2002 | INSTALL EQUIPMENT TO MOVE PRODUCT | $-1,412 | $80,000 | Not Implemented |
GT0725 # 01 Y:2002 | 01 | 2002 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $43,102 | $10,500 | Implemented |
GT0725 # 02 Y:2002 | 02 | 2002 | INSTALL SYSTEM TO COLLECT SCRAP | $540,000 | $192,000 | Not Implemented |
GT0725 # 03 Y:2002 | 03 | 2002 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,758 | $0 | Not Implemented |
GT0725 # 04 Y:2002 | 04 | 2002 | INSTALL SPECTRAL REFLECTORS / DELAMP | $2,446 | $2,550 | Implemented |
GT0725 # 05 Y:2002 | 05 | 2002 | RECOVER WASTE HEAT FROM EQUIPMENT | $10,185 | $35,000 | Not Implemented |
GT0725 # 06 Y:2002 | 06 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,301 | $10,007 | Implemented |
GT0725 # 07 Y:2002 | 07 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,114 | $400 | Implemented |
GT0725 # 08 Y:2002 | 08 | 2002 | FILTER AND REUSE HYDRAULIC OIL | $1,900 | $0 | Implemented |
GT0725 # 09 Y:2002 | 09 | 2002 | CONVERT COMBUSTION EQUIPMENT TO BURN NATURAL GAS | $19,275 | $45,000 | Not Implemented |
BD0201 # 01 Y:2002 | 01 | 2002 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $6,916 | $9,150 | Not Implemented |
BD0201 # 02 Y:2002 | 02 | 2002 | INSTALL AUTOMATIC STACK DAMPER | $4,088 | $15,000 | Not Implemented |
BD0201 # 03 Y:2002 | 03 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,525 | $1,000 | Implemented |
BD0201 # 04 Y:2002 | 04 | 2002 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,064 | $140 | Not Implemented |
BD0201 # 05 Y:2002 | 05 | 2002 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $917 | $1,000 | Not Implemented |
BD0201 # 06 Y:2002 | 06 | 2002 | INSTALL OCCUPANCY SENSORS | $690 | $900 | Not Implemented |
BD0201 # 07 Y:2002 | 07 | 2002 | DISCONNECT BALLASTS | $653 | $240 | Implemented |
BD0201 # 08 Y:2002 | 08 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $368 | $323 | Not Implemented |
BD0201 # 09 Y:2002 | 09 | 2002 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $2,449 | $11,500 | Not Implemented |
BD0201 # 10 Y:2002 | 10 | 2002 | INCREASE USE OF AUTOMATION | $22,464 | $45,000 | Not Implemented |
BD0201 # 11 Y:2002 | 11 | 2002 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $620 | $100 | Implemented |
LL0127 # 01 Y:2002 | 01 | 2002 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $36,202 | $24,480 | Not Implemented |
LL0127 # 02 Y:2002 | 02 | 2002 | USE PHOTOCELL CONTROLS | $17,992 | $946 | Not Implemented |