IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

3,551

matching recommendations
Reset
SIC 265 Paperboard Containers And Boxes
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
AM0320 # 05 Y:1998 05 1998 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED $1,600 $0 Not Implemented
AM0320 # 06 Y:1998 06 1998 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED $1,290 $30 Implemented
AM0320 # 07 Y:1998 07 1998 PAY BILLS ON TIME TO AVOID LATE FEES $763 $0 Implemented
AM0320 # 08 Y:1998 08 1998 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED $390 $0 Implemented
AM0320 # 09 Y:1998 09 1998 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES $265 $635 Implemented
DS0112 # 01 Y:1998 01 1998 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $5,447 $21,490 Implemented
DS0112 # 02 Y:1998 02 1998 USE POWER DURING OFF-PEAK PERIODS $3,019 $1,375 Implemented
DS0112 # 03 Y:1998 03 1998 RECOVER WASTE HEAT FROM EQUIPMENT $12,228 $12,710 Not Implemented
DS0112 # 04 Y:1998 04 1998 RECOVER WASTE HEAT FROM EQUIPMENT $775 $680 Not Implemented
DS0112 # 05 Y:1998 05 1998 IMPROVE HANDLING PRACTICES $360 $352 Not Implemented
DS0112 # 06 Y:1998 06 1998 ESTABLISH EQUIPMENT MAINTENANCE SCHEDULE $259 $0 Implemented
AS0222 # 01 Y:1998 01 1998 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $18,249 $280 Implemented
AS0222 # 02 Y:1998 02 1998 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,087 $3,745 Not Implemented
AS0222 # 03 Y:1998 03 1998 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $3,243 $120 Implemented
AS0222 # 04 Y:1998 04 1998 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $3,365 $60 Implemented
AS0222 # 05 Y:1998 05 1998 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $6,487 $8,291 Implemented
AS0222 # 06 Y:1998 06 1998 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $51,367 $40,600 Not Implemented
AS0222 # 07 Y:1998 07 1998 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $784 $480 Implemented
AS0222 # 08 Y:1998 08 1998 ELIMINATE LEAKS IN WATER LINES AND VALVES $407 $220 Implemented
AS0222 # 09 Y:1998 09 1998 TREAT AND REUSE RINSE WATERS $18,575 $800 Implemented
AS0222 # 10 Y:1998 10 1998 INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE $9,828 $48,000 Not Implemented
AS0222 # 11 Y:1998 11 1998 IMPROVE HANDLING PRACTICES $5,156 $850 Implemented
AS0222 # 12 Y:1998 12 1998 CLEAR AND RENT EXISTING SPACE $67,788 $3,600 Not Implemented
MO0225 # 01 Y:1998 01 1998 UPGRADE CONVEYORS $110,784 $50,000 Not Implemented
MO0225 # 02 Y:1998 02 1998 ADD ADDITIONAL PRODUCTION SHIFT $87,000 $50,000 Not Implemented