Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
113
matching recommendationsSIC | 2652 | Setup Paperboard Boxes |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OD0039 # 06 Y:1995 | 06 | 1995 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $211 | $320 | Implemented |
OD0039 # 07 Y:1995 | 07 | 1995 | INSTALL SET-BACK TIMERS | $579 | $189 | Implemented |
NC0020 # 01 Y:1994 | 01 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $410 | $302 | Implemented |
NC0020 # 02 Y:1994 | 02 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,282 | $3,800 | Implemented |
NC0020 # 03 Y:1994 | 03 | 1994 | USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS | $17,360 | $2,355 | Not Implemented |
NC0020 # 04 Y:1994 | 04 | 1994 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $580 | $55 | Implemented |
NC0020 # 05 Y:1994 | 05 | 1994 | INSULATE BARE EQUIPMENT | $4,029 | $338 | Implemented |
NC0020 # 06 Y:1994 | 06 | 1994 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $1,255 | $4,012 | Implemented |
TN0395 # 01 Y:1990 | 01 | 1990 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $5,279 | $0 | Not Implemented |
TN0395 # 02 Y:1990 | 02 | 1990 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $1,544 | $3,195 | Implemented |
TN0395 # 03 Y:1990 | 03 | 1990 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $3,308 | $300 | Not Implemented |
TN0395 # 04 Y:1990 | 04 | 1990 | KEEP LAMPS AND REFLECTORS CLEAN | $2,426 | $5,083 | Not Implemented |
TN0395 # 05 Y:1990 | 05 | 1990 | INSTALL SET-BACK TIMERS | $1,470 | $0 | Implemented |
TN0395 # 06 Y:1990 | 06 | 1990 | CENTRALIZE CONTROL OF EXHAUST FANS TO ENSURE THEIR SHUTDOWN, OR ESTABLISH PROGRAM TO ENSURE MANUAL SHUTDOWN | $1,403 | $245 | Implemented |
TN0395 # 07 Y:1990 | 07 | 1990 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $568 | $660 | Not Implemented |
TN0395 # 08 Y:1990 | 08 | 1990 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $368 | $0 | Not Implemented |
TN0395 # 09 Y:1990 | 09 | 1990 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $418 | $195 | Implemented |
TN0395 # 10 Y:1990 | 10 | 1990 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $15,293 | $31,800 | Not Implemented |
UD0248 # 01 Y:1988 | 01 | 1988 | COMBINE UTILITY METERS | $1,427 | $0 | Implemented |
UD0248 # 02 Y:1988 | 02 | 1988 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $7,032 | $10,000 | Not Implemented |
UD0248 # 03 Y:1988 | 03 | 1988 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,309 | $400 | Implemented |
UD0248 # 04 Y:1988 | 04 | 1988 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,845 | $360 | Implemented |
UD0248 # 05 Y:1988 | 05 | 1988 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $4,094 | $6,880 | Implemented |
UD0248 # 06 Y:1988 | 06 | 1988 | INSTALL STORM WINDOWS AND DOORS | $6,670 | $4,038 | Implemented |
OK0182 # 01 Y:1985 | 01 | 1985 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $225 | $310 | Implemented |