Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
24
matching recommendationsSIC | 2653 | Corrugated And Solid Fiber Boxes |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0642 # 07 Y:2002 | 07 | 2002 | AIR CONDITION ONLY SPACE NECESSARY | $446 | $0 | Implemented |
OK0642 # 06 Y:2002 | 06 | 2002 | INSTALL SET-BACK TIMERS | $2,130 | $332 | Implemented |
OK0642 # 03 Y:2002 | 03 | 2002 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,265 | $10 | Implemented |
OK0642 # 02 Y:2002 | 02 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,120 | $900 | Implemented |
OK0642 # 01 Y:2002 | 01 | 2002 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $5,760 | $9,780 | Implemented |
OK0447 # 06 Y:1994 | 06 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $815 | $2,199 | Implemented |
OK0447 # 05 Y:1994 | 05 | 1994 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,652 | $832 | Implemented |
OK0447 # 02 Y:1994 | 02 | 1994 | INSULATE BARE EQUIPMENT | $505 | $526 | Implemented |
OK0447 # 01 Y:1994 | 01 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,233 | $8,800 | Implemented |
OK0287 # 03 Y:1989 | 03 | 1989 | IMPROVE LUBRICATION PRACTICES | $438 | $5,122 | Implemented |
OK0287 # 06 Y:1989 | 06 | 1989 | USE RADIANT HEATER FOR SPOT HEATING | $2,087 | $12,000 | Implemented |
OK0287 # 05 Y:1989 | 05 | 1989 | INSTALL TIMERS AND/OR THERMOSTATS | $389 | $980 | Implemented |
OK0197 # 09 Y:1986 | 09 | 1986 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $76 | $47 | Implemented |
OK0197 # 08 Y:1986 | 08 | 1986 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $1,916 | $249 | Implemented |
OK0197 # 07 Y:1986 | 07 | 1986 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,696 | $2,411 | Implemented |
OK0197 # 06 Y:1986 | 06 | 1986 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $817 | $782 | Implemented |
OK0197 # 05 Y:1986 | 05 | 1986 | IMPROVE LUBRICATION PRACTICES | $11,758 | $0 | Implemented |
OK0197 # 04 Y:1986 | 04 | 1986 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $547 | $80 | Implemented |
OK0197 # 01 Y:1986 | 01 | 1986 | MINIMIZE BOILER BLOWDOWN WITH BETTER FEEDWATER TREATMENT | $2,964 | $3,200 | Implemented |
OK0138 # 03 Y:1984 | 03 | 1984 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $916 | $1,209 | Implemented |
OK0138 # 01 Y:1984 | 01 | 1984 | INSTALL TIMERS AND/OR THERMOSTATS | $9,036 | $600 | Implemented |
OK0123 # 02 Y:1984 | 02 | 1984 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,438 | $300 | Implemented |
OK0123 # 04 Y:1984 | 04 | 1984 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $233 | $231 | Implemented |
OK0123 # 03 Y:1984 | 03 | 1984 | INSTALL TIMERS AND/OR THERMOSTATS | $596 | $0 | Implemented |