Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
84
matching recommendationsSIC | 2653 | Corrugated And Solid Fiber Boxes |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LE0336 # 08 Y:2012 | 08 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,616 | $650 | Implemented |
LE0336 # 04 Y:2012 | 04 | 2012 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,734 | $8,000 | Implemented |
LE0336 # 06 Y:2012 | 06 | 2012 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $2,840 | $3,000 | Implemented |
LE0336 # 03 Y:2012 | 03 | 2012 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $6,242 | $16,000 | Implemented |
LE0336 # 07 Y:2012 | 07 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,762 | $25 | Implemented |
LE0336 # 02 Y:2012 | 02 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,173 | $1,000 | Implemented |
LE0336 # 01 Y:2012 | 01 | 2012 | INSTALL TIMERS AND/OR THERMOSTATS | $18,760 | $150 | Implemented |
LE0303 # 11 Y:2010 | 11 | 2010 | RECOVER WASTE HEAT FROM EQUIPMENT | $973 | $1,000 | Implemented |
LE0303 # 10 Y:2010 | 10 | 2010 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,131 | $15 | Implemented |
LE0303 # 09 Y:2010 | 09 | 2010 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,351 | $800 | Implemented |
LE0303 # 01 Y:2010 | 01 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $26,348 | $1,672 | Implemented |
LE0303 # 02 Y:2010 | 02 | 2010 | INSTALL TIMERS AND/OR THERMOSTATS | $10,520 | $650 | Implemented |
LE0270 # 09 Y:2008 | 09 | 2008 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $4,061 | $1,350 | Implemented |
LE0270 # 10 Y:2008 | 10 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,558 | $11,908 | Implemented |
LE0270 # 07 Y:2008 | 07 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,656 | $1,200 | Implemented |
LE0270 # 08 Y:2008 | 08 | 2008 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $6,349 | $175,000 | Implemented |
LE0270 # 04 Y:2008 | 04 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $26,395 | $25,900 | Implemented |
LE0270 # 05 Y:2008 | 05 | 2008 | INSTALL TIMERS AND/OR THERMOSTATS | $20,978 | $250 | Implemented |
LE0270 # 06 Y:2008 | 06 | 2008 | REPAIR OR REPLACE STEAM TRAPS | $10,498 | $3,200 | Implemented |
DL0003 # 04 Y:2007 | 04 | 2007 | USE MINIMUM STEAM OPERATING PRESSURE | $1,497 | $0 | Implemented |
DL0003 # 09 Y:2007 | 09 | 2007 | ESTABLISH EQUIPMENT MAINTENANCE SCHEDULE | $1,892 | $0 | Implemented |
DL0003 # 07 Y:2007 | 07 | 2007 | INSTALL / REPAIR INSULATION ON STEAM LINES | $23,137 | $20,000 | Implemented |
LE0255 # 04 Y:2007 | 04 | 2007 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $19,641 | $29,600 | Implemented |
LE0255 # 05 Y:2007 | 05 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,252 | $1,000 | Implemented |
LE0255 # 01 Y:2007 | 01 | 2007 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $433,831 | $500 | Implemented |