Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
100
matching recommendationsSIC | 2653 | Corrugated And Solid Fiber Boxes |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CO0448 # 08 Y:1999 | 08 | 1999 | DEVELOP STANDARD OPERATING PROCEDURES | $36,000 | $0 | n/a |
CO0448 # 07 Y:1999 | 07 | 1999 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $160,300 | $489,000 | n/a |
CO0448 # 06 Y:1999 | 06 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $20 | $0 | n/a |
CO0448 # 05 Y:1999 | 05 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $330 | $210 | n/a |
CO0448 # 04 Y:1999 | 04 | 1999 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $380 | $150 | n/a |
CO0448 # 03 Y:1999 | 03 | 1999 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $430 | $30 | n/a |
CO0448 # 02 Y:1999 | 02 | 1999 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $830 | $1,080 | n/a |
CO0448 # 01 Y:1999 | 01 | 1999 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $4,820 | $4,000 | n/a |
TN0669 # 01 Y:1999 | 01 | 1999 | TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY | $30,500 | $4,500 | n/a |
TN0669 # 03 Y:1999 | 03 | 1999 | OPTIMIZE PLANT POWER FACTOR | $4,942 | $9,500 | n/a |
TN0669 # 06 Y:1999 | 06 | 1999 | REUSE / RECYCLE/ SELL PAPER PRODUCTS | $1,215 | $600 | n/a |
TN0669 # 02 Y:1999 | 02 | 1999 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $26,935 | $1,075 | n/a |
TN0668 # 01 Y:1999 | 01 | 1999 | REDUCE SCRAP PRODUCTION | $674,570 | $64,500 | Implemented |
TN0668 # 11 Y:1999 | 11 | 1999 | MINIMIZE OPERATION OF EQUIPMENT MAINTAINED IN STANDBY CONDITION | $690 | $0 | Implemented |
TN0668 # 10 Y:1999 | 10 | 1999 | REPAIR AND ELIMINATE STEAM LEAKS | $900 | $196 | Implemented |
TN0668 # 09 Y:1999 | 09 | 1999 | INSULATE BARE EQUIPMENT | $940 | $540 | Implemented |
TN0668 # 08 Y:1999 | 08 | 1999 | METER WASTE WATER | $1,120 | $3,300 | Implemented |
TN0668 # 07 Y:1999 | 07 | 1999 | INSTALL / REPAIR INSULATION ON STEAM LINES | $2,175 | $1,280 | Not Implemented |
TN0668 # 05 Y:1999 | 05 | 1999 | MODIFY CURRENT INCENTIVE PROGRAM | $6,300 | $1,200 | Implemented |
TN0669 # 04 Y:1999 | 04 | 1999 | RECOVER AND REUSE WASTE MATERIAL | $1,875 | $0 | n/a |
TN0668 # 03 Y:1999 | 03 | 1999 | OPTIMIZE PLANT POWER FACTOR | $9,000 | $26,000 | Implemented |
TN0668 # 06 Y:1999 | 06 | 1999 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,696 | $0 | Implemented |
TN0669 # 05 Y:1999 | 05 | 1999 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,601 | $1,620 | n/a |
TN0668 # 02 Y:1999 | 02 | 1999 | CONSIDER USE / PURCHASE OF BULK MATERIALS WHERE POSSIBLE | $238,000 | $110,000 | Not Implemented |
TN0668 # 04 Y:1999 | 04 | 1999 | SEPARATE AND RECYCLE SCRAP METAL TO FOUNDRY OR FOR SALE | $7,860 | $8,370 | Implemented |