IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

248

matching recommendations
Reset
SIC 2653 Corrugated And Solid Fiber Boxes
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
SF0232 # 02 Y:2002 02 2002 INCREASE AMOUNT OF CONDENSATE RETURNED $443 $325 Not Implemented
SF0232 # 03 Y:2002 03 2002 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $300 $294 Not Implemented
SF0232 # 06 Y:2002 06 2002 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $870 $2,355 Not Implemented
SF0232 # 04 Y:2002 04 2002 INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS $1,291 $1,460 Not Implemented
SF0232 # 07 Y:2002 07 2002 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL $1,485 $0 Not Implemented
SF0232 # 08 Y:2002 08 2002 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $7,509 $0 Not Implemented
SF0232 # 01 Y:2002 01 2002 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,269 $0 Implemented
SF0232 # 05 Y:2002 05 2002 USE PHOTOCELL CONTROLS $501 $1,080 Not Implemented
TA0044 # 08 Y:2002 08 2002 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,807 $11,685 Implemented
TA0044 # 09 Y:2002 09 2002 SHUT OFF PILOTS IN STANDBY EQUIPMENT $3,200 $0 Implemented
TA0044 # 07 Y:2002 07 2002 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $6,596 $144 Implemented
TA0044 # 03 Y:2002 03 2002 INSULATE BARE EQUIPMENT $19,880 $2,455 Implemented
TA0044 # 06 Y:2002 06 2002 REPAIR AND ELIMINATE STEAM LEAKS $6,650 $270 Implemented
TA0044 # 10 Y:2002 10 2002 INSTALL / REPAIR INSULATION ON STEAM LINES $225 $180 Implemented
TA0044 # 04 Y:2002 04 2002 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS $9,715 $72 Implemented
TA0044 # 05 Y:2002 05 2002 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA $6,725 $450 Implemented
TA0044 # 01 Y:2002 01 2002 HIRE ADDITIONAL PERSONNEL TO REDUCE CHANGEOUT TIME $114,400 $0 Implemented
TA0044 # 02 Y:2002 02 2002 USE FILTRATION, CENTRIFUGING TO REMOVE CONTAMINANTS $23,976 $65,000 Not Implemented
UU0030 # 02 Y:2002 02 2002 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,250 $390 Implemented
UU0030 # 06 Y:2002 06 2002 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $808 $0 Not Implemented
UU0030 # 03 Y:2002 03 2002 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $379 $240 Not Implemented
UU0030 # 04 Y:2002 04 2002 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $929 $200 Not Implemented
UU0030 # 05 Y:2002 05 2002 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $1,080 $1,843 Not Implemented
UU0030 # 01 Y:2002 01 2002 OPTIMIZE PLANT POWER FACTOR $1,624 $1,800 Implemented
UU0030 # 07 Y:2002 07 2002 USE SYNTHETIC LUBRICANT $1,211 $600 Implemented