Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
248
matching recommendationsSIC | 2653 | Corrugated And Solid Fiber Boxes |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0232 # 02 Y:2002 | 02 | 2002 | INCREASE AMOUNT OF CONDENSATE RETURNED | $443 | $325 | Not Implemented |
SF0232 # 03 Y:2002 | 03 | 2002 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $300 | $294 | Not Implemented |
SF0232 # 06 Y:2002 | 06 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $870 | $2,355 | Not Implemented |
SF0232 # 04 Y:2002 | 04 | 2002 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $1,291 | $1,460 | Not Implemented |
SF0232 # 07 Y:2002 | 07 | 2002 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $1,485 | $0 | Not Implemented |
SF0232 # 08 Y:2002 | 08 | 2002 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $7,509 | $0 | Not Implemented |
SF0232 # 01 Y:2002 | 01 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,269 | $0 | Implemented |
SF0232 # 05 Y:2002 | 05 | 2002 | USE PHOTOCELL CONTROLS | $501 | $1,080 | Not Implemented |
TA0044 # 08 Y:2002 | 08 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,807 | $11,685 | Implemented |
TA0044 # 09 Y:2002 | 09 | 2002 | SHUT OFF PILOTS IN STANDBY EQUIPMENT | $3,200 | $0 | Implemented |
TA0044 # 07 Y:2002 | 07 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,596 | $144 | Implemented |
TA0044 # 03 Y:2002 | 03 | 2002 | INSULATE BARE EQUIPMENT | $19,880 | $2,455 | Implemented |
TA0044 # 06 Y:2002 | 06 | 2002 | REPAIR AND ELIMINATE STEAM LEAKS | $6,650 | $270 | Implemented |
TA0044 # 10 Y:2002 | 10 | 2002 | INSTALL / REPAIR INSULATION ON STEAM LINES | $225 | $180 | Implemented |
TA0044 # 04 Y:2002 | 04 | 2002 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $9,715 | $72 | Implemented |
TA0044 # 05 Y:2002 | 05 | 2002 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $6,725 | $450 | Implemented |
TA0044 # 01 Y:2002 | 01 | 2002 | HIRE ADDITIONAL PERSONNEL TO REDUCE CHANGEOUT TIME | $114,400 | $0 | Implemented |
TA0044 # 02 Y:2002 | 02 | 2002 | USE FILTRATION, CENTRIFUGING TO REMOVE CONTAMINANTS | $23,976 | $65,000 | Not Implemented |
UU0030 # 02 Y:2002 | 02 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,250 | $390 | Implemented |
UU0030 # 06 Y:2002 | 06 | 2002 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $808 | $0 | Not Implemented |
UU0030 # 03 Y:2002 | 03 | 2002 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $379 | $240 | Not Implemented |
UU0030 # 04 Y:2002 | 04 | 2002 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $929 | $200 | Not Implemented |
UU0030 # 05 Y:2002 | 05 | 2002 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,080 | $1,843 | Not Implemented |
UU0030 # 01 Y:2002 | 01 | 2002 | OPTIMIZE PLANT POWER FACTOR | $1,624 | $1,800 | Implemented |
UU0030 # 07 Y:2002 | 07 | 2002 | USE SYNTHETIC LUBRICANT | $1,211 | $600 | Implemented |