IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

3,112

matching recommendations
Reset
SIC 267 Misc. Converted Paper Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
LE0316 # 11 Y:2011 11 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,567 $3,205 Not Implemented
LE0316 # 12 Y:2011 12 2011 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,182 $1,000 Not Implemented
LE0316 # 13 Y:2011 13 2011 INSTALL SKYLIGHTS $1,030 $22,500 Not Implemented
NC0421 # 01 Y:2011 01 2011 PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT $28,591 $51,300 Not Implemented
NC0421 # 02 Y:2011 02 2011 USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER $9,751 $25,000 Not Implemented
NC0421 # 03 Y:2011 03 2011 REPAIR OR REPLACE STEAM TRAPS $12,484 $5,500 Implemented
NC0421 # 04 Y:2011 04 2011 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $10,180 $25,000 Not Implemented
NC0421 # 05 Y:2011 05 2011 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $4,844 $100 Implemented
NC0421 # 06 Y:2011 06 2011 DEVELOP A REPAIR/REPLACE POLICY $9,751 $20,768 Implemented
UA3009 # 01 Y:2011 01 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $16,823 $18,375 Not Implemented
UA3009 # 02 Y:2011 02 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,597 $265 Implemented
UA3009 # 03 Y:2011 03 2011 INSTALL OCCUPANCY SENSORS $592 $623 Implemented
UA3009 # 04 Y:2011 04 2011 INSTALL TIMERS AND/OR THERMOSTATS $51,741 $7,700 Not Implemented
UA3009 # 05 Y:2011 05 2011 USE RADIANT HEATER FOR SPOT HEATING $2,427 $3,004 Not Implemented
UA3009 # 06 Y:2011 06 2011 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $8,000 $800 Not Implemented
UA3009 # 07 Y:2011 07 2011 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $15,274 $5,000 Implemented
UA3009 # 08 Y:2011 08 2011 USE FLUE GASES TO HEAT PROCESS OR SERVICE WATER $22,812 $64,000 Not Implemented
UA3009 # 09 Y:2011 09 2011 INSULATE BARE EQUIPMENT $7,844 $1,950 Not Implemented
UA3009 # 10 Y:2011 10 2011 METER WASTE WATER $55,751 $7,500 n/a
BD0376 # 01 Y:2010 01 2010 REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES $105,011 $51,500 Implemented
BD0376 # 02 Y:2010 02 2010 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $67,200 $125 Not Implemented
BD0376 # 03 Y:2010 03 2010 RECOVER WASTE HEAT FROM EQUIPMENT $62,913 $70,000 Implemented
BD0376 # 04 Y:2010 04 2010 RECOVER WASTE HEAT FROM EQUIPMENT $39,238 $34,000 Implemented
BD0376 # 05 Y:2010 05 2010 INSTALL TURBULATORS $20,378 $4,350 Not Implemented
BD0376 # 06 Y:2010 06 2010 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $11,590 $5,500 Implemented