Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
622
matching recommendationsSIC | 2671 | Paper Coated & Laminated, Packaging |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LE0542 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,207 | $1,900 | Implemented |
LE0542 # 01 Y:2023 | 01 | 2023 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,677 | $3,000 | Not Implemented |
CC0007 # 08 Y:2022 | 08 | 2022 | USE COOLING TOWER WATER INSTEAD OF REFRIGERATION | $15,506 | $58,000 | n/a |
CC0007 # 07 Y:2022 | 07 | 2022 | RECOVER WASTE HEAT FROM EQUIPMENT | $10,680 | $40,000 | n/a |
CC0007 # 06 Y:2022 | 06 | 2022 | INSULATE BARE EQUIPMENT | $3,056 | $8,000 | n/a |
CC0007 # 05 Y:2022 | 05 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,005 | $1,000 | n/a |
CC0007 # 09 Y:2022 | 09 | 2022 | REPAIR AND ELIMINATE STEAM LEAKS | $8,453 | $500 | n/a |
CC0007 # 03 Y:2022 | 03 | 2022 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $364 | $0 | n/a |
CC0007 # 04 Y:2022 | 04 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,805 | $18,800 | n/a |
CC0007 # 02 Y:2022 | 02 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,936 | $4,400 | n/a |
CC0007 # 01 Y:2022 | 01 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $5,092 | $17,800 | n/a |
UW2202 # 02 Y:2022 | 02 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,233 | $12,913 | Implemented |
UW2202 # 03 Y:2022 | 03 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $8,538 | $9,763 | Implemented |
UW2202 # 04 Y:2022 | 04 | 2022 | USE SOLAR HEAT TO MAKE ELECTRICTY | $135,581 | $876,160 | Implemented |
UW2202 # 01 Y:2022 | 01 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $16,645 | $10,782 | Implemented |
LE0516 # 01 Y:2021 | 01 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,511 | $200 | Implemented |
LE0516 # 02 Y:2021 | 02 | 2021 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,124 | $1,200 | Implemented |
LE0516 # 03 Y:2021 | 03 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $14,984 | $30,000 | Not Implemented |
LE0516 # 05 Y:2021 | 05 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,118 | $11,000 | Not Implemented |
LE0516 # 04 Y:2021 | 04 | 2021 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $8,448 | $25,000 | Not Implemented |
LE0516 # 06 Y:2021 | 06 | 2021 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $5,727 | $36,000 | Not Implemented |
UF0557 # 03 Y:2020 | 03 | 2020 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $33,607 | $165,000 | Implemented |
UF0557 # 06 Y:2020 | 06 | 2020 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $8,554 | $38,357 | Not Implemented |
UF0557 # 08 Y:2020 | 08 | 2020 | INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN | $3,710 | $5,998 | Implemented |
UF0557 # 07 Y:2020 | 07 | 2020 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $7,282 | $25,340 | Implemented |