Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
24
matching recommendationsSIC | 2674 | Bags: Uncoated Paper & Multiwall |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SD0459 # 01 Y:2012 | 01 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $18,564 | $2,200 | Implemented |
SD0459 # 02 Y:2012 | 02 | 2012 | USE PHOTOCELL CONTROLS | $4,256 | $7,400 | Not Implemented |
SD0459 # 03 Y:2012 | 03 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,717 | $200 | Not Implemented |
SD0459 # 04 Y:2012 | 04 | 2012 | INSTALL OCCUPANCY SENSORS | $1,059 | $845 | Not Implemented |
SD0459 # 05 Y:2012 | 05 | 2012 | USE MINIMUM STEAM OPERATING PRESSURE | $276 | $200 | Implemented |
SF0396 # 11 Y:2011 | 11 | 2011 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $13,167 | $64,213 | Not Implemented |
SF0396 # 10 Y:2011 | 10 | 2011 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $5,040 | $23,228 | Implemented |
SF0396 # 09 Y:2011 | 09 | 2011 | TURN OFF EQUIPMENT WHEN NOT IN USE | $583 | $2,107 | Implemented |
SF0396 # 08 Y:2011 | 08 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,045 | $22,410 | Implemented |
SF0396 # 07 Y:2011 | 07 | 2011 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $4,598 | $12,809 | Not Implemented |
SF0396 # 06 Y:2011 | 06 | 2011 | REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES | $605 | $1,540 | Implemented |
SF0396 # 05 Y:2011 | 05 | 2011 | INSTALL OCCUPANCY SENSORS | $5,645 | $7,073 | Implemented |
SF0396 # 04 Y:2011 | 04 | 2011 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $339 | $310 | Implemented |
SF0396 # 03 Y:2011 | 03 | 2011 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,230 | $1,731 | Not Implemented |
SF0396 # 02 Y:2011 | 02 | 2011 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $1,498 | $1,199 | Implemented |
SF0396 # 01 Y:2011 | 01 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,923 | $0 | Implemented |
SD0298 # 08 Y:2002 | 08 | 2002 | PAY UTILITY BILLS ON TIME | $7,456 | $0 | Not Implemented |
SD0298 # 07 Y:2002 | 07 | 2002 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $8,422 | $10,000 | Implemented |
SD0298 # 06 Y:2002 | 06 | 2002 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $2,446 | $0 | Not Implemented |
SD0298 # 05 Y:2002 | 05 | 2002 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $2,448 | $2,560 | Implemented |
SD0298 # 04 Y:2002 | 04 | 2002 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,115 | $6,000 | Not Implemented |
SD0298 # 03 Y:2002 | 03 | 2002 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $4,898 | $1,000 | Not Implemented |
SD0298 # 02 Y:2002 | 02 | 2002 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $5,989 | $1,000 | Not Implemented |
SD0298 # 01 Y:2002 | 01 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,966 | $720 | Implemented |