Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
17
matching recommendationsSIC | 2674 | Bags: Uncoated Paper & Multiwall |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
BD0432 # 07 Y:2013 | 07 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $378 | $20 | Not Implemented |
BD0432 # 06 Y:2013 | 06 | 2013 | SHUT OFF PILOTS IN STANDBY EQUIPMENT | $212 | $40 | Not Implemented |
BD0432 # 05 Y:2013 | 05 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $793 | $2,777 | Not Implemented |
BD0432 # 04 Y:2013 | 04 | 2013 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,312 | $500 | Not Implemented |
BD0432 # 03 Y:2013 | 03 | 2013 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,832 | $4,800 | Not Implemented |
BD0432 # 02 Y:2013 | 02 | 2013 | ADJUST / MAINTAIN FORK LIFT TRUCKS FOR MOST EFFICIENT OPERATION | $6,185 | $16,000 | Not Implemented |
BD0432 # 01 Y:2013 | 01 | 2013 | USE RADIANT HEATER FOR SPOT HEATING | $9,498 | $14,512 | Not Implemented |
BD0158 # 05 Y:2000 | 05 | 2000 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $600 | $240 | Implemented |
BD0158 # 06 Y:2000 | 06 | 2000 | ELIMINATE OLD STOCK AND MODIFY INVENTORY CONTROL | $631,800 | $50,000 | Implemented |
BD0158 # 04 Y:2000 | 04 | 2000 | TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY | $13,680 | $5,000 | Not Implemented |
BD0158 # 03 Y:2000 | 03 | 2000 | INSTALL AUTOMATIC STACK DAMPER | $1,929 | $3,000 | Implemented |
BD0158 # 02 Y:2000 | 02 | 2000 | INSTALL OCCUPANCY SENSORS | $4,276 | $1,650 | Not Implemented |
BD0158 # 01 Y:2000 | 01 | 2000 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $17,993 | $20,000 | Not Implemented |
BD0011 # 01 Y:1994 | 01 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $9,085 | $18,280 | Implemented |
BD0011 # 04 Y:1994 | 04 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,614 | $5,757 | Implemented |
BD0011 # 03 Y:1994 | 03 | 1994 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,481 | $20 | Not Implemented |
BD0011 # 02 Y:1994 | 02 | 1994 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,003 | $750 | Not Implemented |