Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,540
matching recommendationsSIC | 27 | Printing And Publishing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WI0080 # 01 Y:1990 | 01 | 1990 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $32,758 | $0 | Implemented |
WI0080 # 04 Y:1990 | 04 | 1990 | INSTALL STORM WINDOWS AND DOORS | $1,672 | $2,640 | Implemented |
WI0080 # 05 Y:1990 | 05 | 1990 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,274 | $500 | Implemented |
WI0080 # 06 Y:1990 | 06 | 1990 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,098 | $0 | Implemented |
WI0080 # 07 Y:1990 | 07 | 1990 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $520 | $1,250 | Implemented |
UD0311 # 01 Y:1990 | 01 | 1990 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $5,733 | $2,400 | Implemented |
UD0311 # 03 Y:1990 | 03 | 1990 | AVOID INTRODUCING HOT, HUMID, OR DIRTY AIR INTO HVAC SYSTEM | $549 | $0 | Implemented |
WI0079 # 01 Y:1990 | 01 | 1990 | INSTALL TIMERS AND/OR THERMOSTATS | $2,834 | $750 | Implemented |
WI0079 # 03 Y:1990 | 03 | 1990 | INSTALL TIMERS AND/OR THERMOSTATS | $1,365 | $1,000 | Implemented |
WI0079 # 04 Y:1990 | 04 | 1990 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $1,128 | $5,000 | Implemented |
WI0079 # 07 Y:1990 | 07 | 1990 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $68 | $500 | Implemented |
WI0079 # 08 Y:1990 | 08 | 1990 | INSTALL STORM WINDOWS AND DOORS | $96 | $270 | Implemented |
UD0309 # 02 Y:1990 | 02 | 1990 | INSTALL TIMERS AND/OR THERMOSTATS | $3,951 | $700 | Implemented |
UD0309 # 03 Y:1990 | 03 | 1990 | AIR CONDITION ONLY SPACE NECESSARY | $1,295 | $200 | Implemented |
UD0309 # 06 Y:1990 | 06 | 1990 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $8,028 | $10,000 | Implemented |
UD0310 # 02 Y:1990 | 02 | 1990 | SHUT OFF PILOTS IN STANDBY EQUIPMENT | $862 | $0 | Implemented |
UD0310 # 03 Y:1990 | 03 | 1990 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $170 | $0 | Implemented |
UD0310 # 04 Y:1990 | 04 | 1990 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,326 | $442 | Implemented |
UD0310 # 05 Y:1990 | 05 | 1990 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $907 | $1,800 | Implemented |
AM0078 # 01 Y:1990 | 01 | 1990 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $4,600 | $0 | Implemented |
AM0078 # 03 Y:1990 | 03 | 1990 | ISOLATE HOT OR COLD EQUIPMENT | $1,090 | $500 | Implemented |
AM0078 # 04 Y:1990 | 04 | 1990 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $810 | $550 | Implemented |
OR0074 # 01 Y:1989 | 01 | 1989 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $171 | $223 | Implemented |
OR0074 # 03 Y:1989 | 03 | 1989 | OPTIMIZE PLANT POWER FACTOR | $498 | $1,125 | Implemented |
OR0074 # 04 Y:1989 | 04 | 1989 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $200 | $250 | Implemented |