Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
335
matching recommendationsSIC | 27 | Printing And Publishing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MZ0342 # 05 Y:2023 | 05 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,266 | $5,828 | Implemented |
MZ0342 # 01 Y:2023 | 01 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $433 | $220 | Not Implemented |
MZ0342 # 02 Y:2023 | 02 | 2023 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $157 | $80 | Not Implemented |
MZ0342 # 03 Y:2023 | 03 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $570 | $120 | Implemented |
MZ0342 # 04 Y:2023 | 04 | 2023 | INSTALL OCCUPANCY SENSORS | $5,030 | $3,700 | Implemented |
MZ0171 # 01 Y:2015 | 01 | 2015 | AIR CONDITION ONLY SPACE NECESSARY | $1,588 | $0 | Not Implemented |
MZ0171 # 03 Y:2015 | 03 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,759 | $3,900 | Not Implemented |
MZ0171 # 04 Y:2015 | 04 | 2015 | INSTALL OCCUPANCY SENSORS | $2,783 | $880 | Not Implemented |
MZ0171 # 02 Y:2015 | 02 | 2015 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $8,781 | $0 | Not Implemented |
MZ0171 # 05 Y:2015 | 05 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,558 | $870 | Not Implemented |
MZ0080 # 03 Y:2012 | 03 | 2012 | CONDENSE OPERATION INTO ONE BUILDING | $13,624 | $0 | Implemented |
MZ0080 # 05 Y:2012 | 05 | 2012 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $12,554 | $0 | Not Implemented |
MZ0080 # 07 Y:2012 | 07 | 2012 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $306 | $0 | Not Implemented |
MZ0080 # 06 Y:2012 | 06 | 2012 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $2,548 | $600 | Implemented |
MZ0080 # 02 Y:2012 | 02 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $28,028 | $35,700 | Implemented |
MZ0080 # 01 Y:2012 | 01 | 2012 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $10,819 | $0 | Implemented |
MZ0080 # 04 Y:2012 | 04 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,580 | $850 | Implemented |
MZ0078 # 10 Y:2012 | 10 | 2012 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $34,576 | $40,759 | Implemented |
MZ0078 # 07 Y:2012 | 07 | 2012 | MAKE ICE DURING OFF PEAK HOURS FOR COOLING | $9,573 | $9,800 | Not Implemented |
MZ0078 # 11 Y:2012 | 11 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $889 | $432 | Implemented |
MZ0078 # 08 Y:2012 | 08 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $888 | $0 | Implemented |
MZ0078 # 12 Y:2012 | 12 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,463 | $8,000 | Implemented |
MZ0078 # 02 Y:2012 | 02 | 2012 | INSTALL OCCUPANCY SENSORS | $126 | $760 | Implemented |
MZ0078 # 03 Y:2012 | 03 | 2012 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $2,256 | $320 | Not Implemented |
MZ0078 # 04 Y:2012 | 04 | 2012 | SCHEDULE ROUTINE MAINTENANCE DURING NON-OPERATING PERIODS | $10,070 | $0 | Implemented |