Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
26
matching recommendationsSIC | 27 | Printing And Publishing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MS0242 # 11 Y:2004 | 11 | 2004 | APPLY FOR INVESTMENT INCENTIVES | $48 | $50 | Not Implemented |
MS0242 # 10 Y:2004 | 10 | 2004 | INSTALL / REPAIR INSULATION ON STEAM LINES | $297 | $48 | Not Implemented |
MS0242 # 09 Y:2004 | 09 | 2004 | USE PHOTOCELL CONTROLS | $470 | $222 | Not Implemented |
MS0242 # 08 Y:2004 | 08 | 2004 | PAY BILLS ON TIME TO AVOID LATE FEES | $753 | $234 | Not Implemented |
MS0242 # 07 Y:2004 | 07 | 2004 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $1,381 | $0 | Not Implemented |
MS0242 # 06 Y:2004 | 06 | 2004 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,170 | $371 | Not Implemented |
MS0242 # 05 Y:2004 | 05 | 2004 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $3,122 | $300 | Not Implemented |
MS0242 # 04 Y:2004 | 04 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,247 | $1,061 | Implemented |
MS0242 # 03 Y:2004 | 03 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $17,550 | $19,555 | n/a |
MS0242 # 02 Y:2004 | 02 | 2004 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $34,758 | $50,000 | Not Implemented |
MS0242 # 01 Y:2004 | 01 | 2004 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $75,363 | $327,360 | Not Implemented |
MS0127 # 07 Y:1999 | 07 | 1999 | CONDENSE OPERATION INTO ONE BUILDING | $115,929 | $8,265 | Not Implemented |
MS0127 # 08 Y:1999 | 08 | 1999 | INSTALL SHELVES / RACKS TO UTILIZE UNUSED SPACE | $156,180 | $23,010 | Implemented |
MS0127 # 06 Y:1999 | 06 | 1999 | USE RE-USABLE FILTERS | $14,954 | $14,960 | Not Implemented |
MS0127 # 05 Y:1999 | 05 | 1999 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $393 | $101 | Not Implemented |
MS0127 # 04 Y:1999 | 04 | 1999 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $3,782 | $11,500 | Not Implemented |
MS0127 # 03 Y:1999 | 03 | 1999 | SHUT OFF PILOTS IN STANDBY EQUIPMENT | $140 | $54 | Implemented |
MS0127 # 02 Y:1999 | 02 | 1999 | INSTALL TIMERS AND/OR THERMOSTATS | $584 | $236 | Implemented |
MS0127 # 01 Y:1999 | 01 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $11,685 | $1,202 | Implemented |
MS0058 # 01 Y:1996 | 01 | 1996 | INSTALL TIMERS AND/OR THERMOSTATS | $4,932 | $2,552 | Not Implemented |
MS0058 # 07 Y:1996 | 07 | 1996 | USE RE-USABLE FILTERS | $4,251 | $5,190 | Not Implemented |
MS0058 # 06 Y:1996 | 06 | 1996 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $507 | $261 | Not Implemented |
MS0058 # 05 Y:1996 | 05 | 1996 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,219 | $288 | Not Implemented |
MS0058 # 04 Y:1996 | 04 | 1996 | REDUCE VENTILATION AIR | $11,167 | $3,016 | Not Implemented |
MS0058 # 03 Y:1996 | 03 | 1996 | USE SYNTHETIC LUBRICANT | $3,493 | $410 | Not Implemented |