Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
287
matching recommendationsSIC | 27 | Printing And Publishing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0123 # 03 Y:1991 | 03 | 1991 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $769 | $2,520 | Not Implemented |
AM0123 # 04 Y:1991 | 04 | 1991 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $490 | $0 | Not Implemented |
AM0123 # 05 Y:1991 | 05 | 1991 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $480 | $200 | Not Implemented |
AM0123 # 06 Y:1991 | 06 | 1991 | INSTALL SET-BACK TIMERS | $472 | $0 | Not Implemented |
AM0123 # 07 Y:1991 | 07 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $100 | $100 | Not Implemented |
AM0115 # 01 Y:1991 | 01 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,348 | $0 | Not Implemented |
AM0115 # 02 Y:1991 | 02 | 1991 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $3,600 | $7,000 | Not Implemented |
AM0115 # 03 Y:1991 | 03 | 1991 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $2,020 | $3,220 | Not Implemented |
AM0115 # 04 Y:1991 | 04 | 1991 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $923 | $40 | Not Implemented |
AM0115 # 05 Y:1991 | 05 | 1991 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $240 | $0 | Not Implemented |
AM0115 # 06 Y:1991 | 06 | 1991 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $140 | $213 | Not Implemented |
AM0078 # 01 Y:1990 | 01 | 1990 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $4,600 | $0 | Implemented |
AM0078 # 02 Y:1990 | 02 | 1990 | IMPROVE LUBRICATION PRACTICES | $2,010 | $0 | Not Implemented |
AM0078 # 03 Y:1990 | 03 | 1990 | ISOLATE HOT OR COLD EQUIPMENT | $1,090 | $500 | Implemented |
AM0078 # 04 Y:1990 | 04 | 1990 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $810 | $550 | Implemented |
LT0120 # 01 Y:1988 | 01 | 1988 | INSTALL TIMERS AND/OR THERMOSTATS | $3,260 | $1,520 | Not Implemented |
LT0120 # 02 Y:1988 | 02 | 1988 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,757 | $1,250 | Implemented |
LT0120 # 03 Y:1988 | 03 | 1988 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,841 | $1,172 | Implemented |
LT0120 # 04 Y:1988 | 04 | 1988 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $896 | $0 | Implemented |
LT0120 # 05 Y:1988 | 05 | 1988 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $161 | $398 | Not Implemented |
AM0010 # 01 Y:1987 | 01 | 1987 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,664 | $69 | Not Implemented |
AM0010 # 02 Y:1987 | 02 | 1987 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,314 | $177 | Implemented |
AM0010 # 03 Y:1987 | 03 | 1987 | UTILIZE OUTSIDE AIR INSTEAD OF CONDITIONED AIR FOR DRYING | $1,886 | $2,394 | Implemented |
AM0010 # 04 Y:1987 | 04 | 1987 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $835 | $689 | Implemented |
AM0009 # 01 Y:1987 | 01 | 1987 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $3,552 | $8,250 | Implemented |