Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,640
matching recommendationsSIC | 27 | Printing And Publishing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WI0128 # 04 Y:1991 | 04 | 1991 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $704 | $2,800 | Implemented |
WI0128 # 05 Y:1991 | 05 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $633 | $144 | Implemented |
WI0128 # 06 Y:1991 | 06 | 1991 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $331 | $700 | Implemented |
WI0128 # 07 Y:1991 | 07 | 1991 | RECOVER WASTE HEAT FROM EQUIPMENT | $104 | $500 | Implemented |
AM0129 # 01 Y:1991 | 01 | 1991 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $243 | $336 | Not Implemented |
AM0129 # 02 Y:1991 | 02 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $746 | $0 | Not Implemented |
AM0129 # 03 Y:1991 | 03 | 1991 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $660 | $755 | Not Implemented |
AM0129 # 04 Y:1991 | 04 | 1991 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $2,875 | $32 | Not Implemented |
AM0129 # 05 Y:1991 | 05 | 1991 | INSTALL OR UPGRADE INSULATION ON HVAC DISTRIBUTION SYSTEMS | $370 | $0 | Not Implemented |
AM0129 # 06 Y:1991 | 06 | 1991 | OPTIMIZE PLANT POWER FACTOR | $2,350 | $2,000 | Not Implemented |
WI0125 # 01 Y:1991 | 01 | 1991 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $3,023 | $0 | Implemented |
WI0125 # 02 Y:1991 | 02 | 1991 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $1,987 | $0 | Implemented |
WI0125 # 03 Y:1991 | 03 | 1991 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $721 | $700 | Implemented |
WI0125 # 04 Y:1991 | 04 | 1991 | IMPROVE LUBRICATION PRACTICES | $567 | $0 | Implemented |
WI0125 # 05 Y:1991 | 05 | 1991 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $437 | $1,280 | Implemented |
WI0125 # 06 Y:1991 | 06 | 1991 | INSTALL SET-BACK TIMERS | $373 | $200 | Implemented |
WI0125 # 07 Y:1991 | 07 | 1991 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $175 | $0 | Implemented |
WI0122 # 01 Y:1991 | 01 | 1991 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $2,922 | $5,000 | Not Implemented |
WI0122 # 02 Y:1991 | 02 | 1991 | INSULATE BARE EQUIPMENT | $162 | $165 | Not Implemented |
WI0122 # 03 Y:1991 | 03 | 1991 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $1,896 | $10,000 | Not Implemented |
WI0122 # 04 Y:1991 | 04 | 1991 | AIR CONDITION ONLY SPACE NECESSARY | $1,554 | $1,000 | Not Implemented |
WI0122 # 05 Y:1991 | 05 | 1991 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $744 | $1,400 | Not Implemented |
WI0122 # 06 Y:1991 | 06 | 1991 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $1,487 | $1,400 | Not Implemented |
WI0122 # 07 Y:1991 | 07 | 1991 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $937 | $0 | Not Implemented |
WI0122 # 08 Y:1991 | 08 | 1991 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $557 | $640 | Not Implemented |