Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,640
matching recommendationsSIC | 27 | Printing And Publishing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SU0181 # 02 Y:2004 | 02 | 2004 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $8,932 | $0 | Not Implemented |
SU0181 # 03 Y:2004 | 03 | 2004 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $1,560 | $0 | Not Implemented |
SU0181 # 04 Y:2004 | 04 | 2004 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $4,821 | $264 | Not Implemented |
SU0181 # 05 Y:2004 | 05 | 2004 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $15,188 | $1,545 | Implemented |
SU0181 # 06 Y:2004 | 06 | 2004 | USE SYNTHETIC LUBRICANT | $7,821 | $1,000 | Not Implemented |
SU0181 # 07 Y:2004 | 07 | 2004 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $2,229 | $368 | Implemented |
SU0181 # 08 Y:2004 | 08 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $12,202 | $6,469 | Not Implemented |
GT0779 # 01 Y:2004 | 01 | 2004 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $1,183 | $5,000 | Implemented |
GT0779 # 02 Y:2004 | 02 | 2004 | REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS | $590 | $2,700 | Implemented |
GT0779 # 03 Y:2004 | 03 | 2004 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,642 | $5,350 | Not Implemented |
GT0779 # 04 Y:2004 | 04 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $327 | $300 | Implemented |
GT0779 # 05 Y:2004 | 05 | 2004 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $2,090 | $4,600 | Not Implemented |
GT0779 # 06 Y:2004 | 06 | 2004 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,561 | $320 | Not Implemented |
GT0779 # 07 Y:2004 | 07 | 2004 | INSTALL OCCUPANCY SENSORS | $303 | $1,000 | Implemented |
IA0338 # 01 Y:2004 | 01 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $457 | $189 | Implemented |
IA0338 # 02 Y:2004 | 02 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,036 | $20 | Implemented |
IA0338 # 03 Y:2004 | 03 | 2004 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $895 | $2,750 | Implemented |
IA0338 # 04 Y:2004 | 04 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,854 | $5,572 | Implemented |
IA0338 # 05 Y:2004 | 05 | 2004 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $462 | $0 | Implemented |
IA0338 # 06 Y:2004 | 06 | 2004 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $74,749 | $162,500 | Implemented |
SU0179 # 01 Y:2004 | 01 | 2004 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $12,807 | $0 | Not Implemented |
SU0179 # 02 Y:2004 | 02 | 2004 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $543 | $0 | Not Implemented |
SU0179 # 03 Y:2004 | 03 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,108 | $6,327 | Not Implemented |
SU0179 # 04 Y:2004 | 04 | 2004 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,671 | $2,665 | Not Implemented |
SU0179 # 05 Y:2004 | 05 | 2004 | OPTIMIZE PLANT POWER FACTOR | $3,469 | $6,227 | Not Implemented |