IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

84

matching recommendations
Reset
SIC 27 Printing And Publishing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
DL0106 # 02 Y:2013 02 2013 TURN OFF EQUIPMENT WHEN NOT IN USE $28,083 $1,516 Implemented
DL0106 # 04 Y:2013 04 2013 REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL $102,000 $2,375,000 Implemented
DL0106 # 01 Y:2013 01 2013 REDUCE VENTILATION AIR $50,820 $2,200 Implemented
LE0360 # 08 Y:2013 08 2013 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $366 $80 Implemented
LE0360 # 06 Y:2013 06 2013 RECOVER WASTE HEAT FROM EQUIPMENT $1,806 $3,200 Implemented
LE0360 # 01 Y:2013 01 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,056 $8,300 Implemented
LE0360 # 09 Y:2013 09 2013 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT $691 $700 Implemented
LE0360 # 10 Y:2013 10 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,342 $1,000 Implemented
LE0223 # 03 Y:2005 03 2005 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA $4,650 $50 Implemented
LE0223 # 05 Y:2005 05 2005 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,281 $100 Implemented
LE0223 # 04 Y:2005 04 2005 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $2,831 $2,500 Implemented
LE0223 # 06 Y:2005 06 2005 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $1,391 $250 Implemented
LE0223 # 10 Y:2005 10 2005 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,460 $0 Implemented
LE0223 # 08 Y:2005 08 2005 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $457 $1,000 Implemented
LE0223 # 09 Y:2005 09 2005 INSTALL OCCUPANCY SENSORS $375 $300 Implemented
LE0223 # 07 Y:2005 07 2005 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $844 $80 Implemented
LE0149 # 07 Y:2002 07 2002 INSTALL OCCUPANCY SENSORS $472 $75 Implemented
LE0149 # 05 Y:2002 05 2002 PREHEAT COMBUSTION AIR WITH WASTE HEAT $11,578 $25,000 Implemented
LE0149 # 06 Y:2002 06 2002 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $886 $750 Implemented
LE0149 # 03 Y:2002 03 2002 INSULATE BARE EQUIPMENT $1,441 $260 Implemented
LE0149 # 01 Y:2002 01 2002 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $4,655 $340 Implemented
LE0149 # 02 Y:2002 02 2002 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $7,182 $1,000 Implemented
LE0149 # 04 Y:2002 04 2002 RECOVER WASTE HEAT FROM EQUIPMENT $1,547 $1,200 Implemented
LE0149 # 08 Y:2002 08 2002 INSTALL TIMERS AND/OR THERMOSTATS $4,252 $2,100 Implemented
LE0104 # 04 Y:2001 04 2001 IMPROVE LUBRICATION PRACTICES $378 $400 Implemented