Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
43
matching recommendationsSIC | 271 | Newspapers |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0695 # 02 Y:2015 | 02 | 2015 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $9,660 | $0 | Implemented |
AM0695 # 01 Y:2015 | 01 | 2015 | OPTIMIZE PLANT POWER FACTOR | $9,060 | $12,550 | Not Implemented |
AM0695 # 08 Y:2015 | 08 | 2015 | INSTALL OCCUPANCY SENSORS | $150 | $170 | Not Implemented |
AM0695 # 07 Y:2015 | 07 | 2015 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $1,350 | $540 | Implemented |
AM0695 # 06 Y:2015 | 06 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $390 | $4 | Not Implemented |
AM0695 # 05 Y:2015 | 05 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $800 | $200 | Implemented |
AM0695 # 04 Y:2015 | 04 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $875 | $520 | Implemented |
AM0695 # 03 Y:2015 | 03 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,170 | $1,660 | Implemented |
MI0276 # 06 Y:2015 | 06 | 2015 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $6,524 | $6,280 | Implemented |
MI0276 # 05 Y:2015 | 05 | 2015 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $6,998 | $2,680 | Implemented |
MI0276 # 04 Y:2015 | 04 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $9,296 | $40 | Implemented |
MI0276 # 03 Y:2015 | 03 | 2015 | INSTALL OCCUPANCY SENSORS | $11,055 | $676 | Implemented |
MI0276 # 02 Y:2015 | 02 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $24,948 | $1,660 | Implemented |
MI0276 # 01 Y:2015 | 01 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $25,305 | $11,600 | Not Implemented |
MI0276 # 07 Y:2015 | 07 | 2015 | AIR CONDITION ONLY SPACE NECESSARY | $5,757 | $1,500 | Not Implemented |
MI0276 # 08 Y:2015 | 08 | 2015 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $4,632 | $570 | Implemented |
MI0276 # 13 Y:2015 | 13 | 2015 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $831 | $20 | Implemented |
MI0276 # 09 Y:2015 | 09 | 2015 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $4,481 | $12,150 | Not Implemented |
MI0276 # 11 Y:2015 | 11 | 2015 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,371 | $3,309 | Implemented |
MI0276 # 12 Y:2015 | 12 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,078 | $1,638 | Implemented |
MI0276 # 10 Y:2015 | 10 | 2015 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $3,212 | $40 | Implemented |
MI0273 # 06 Y:2015 | 06 | 2015 | LOWER LIGHT FIXTURES IN HIGH CEILING AREAS | $6,562 | $16,470 | Not Implemented |
MI0273 # 05 Y:2015 | 05 | 2015 | INSTALL OCCUPANCY SENSORS | $6,933 | $912 | Implemented |
MI0273 # 04 Y:2015 | 04 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,969 | $1,660 | Implemented |
MI0273 # 03 Y:2015 | 03 | 2015 | MINIMIZE WATER USAGE | $8,287 | $16,600 | Not Implemented |