IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

3,301

matching recommendations
Reset
SIC 275 Commercial Printing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OD0127 # 01 Y:1999 01 1999 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,954 $5,472 Implemented
OD0127 # 02 Y:1999 02 1999 SHUT OFF PILOTS IN STANDBY EQUIPMENT $477 $80 Not Implemented
OD0127 # 03 Y:1999 03 1999 ELIMINATE LEAKS IN WATER LINES AND VALVES $3,582 $240 Implemented
OD0127 # 04 Y:1999 04 1999 COMBINE UTILITY METERS $9,570 $5,000 Implemented
SF0157 # 01 Y:1999 01 1999 INSTALL OCCUPANCY SENSORS $1,834 $1,456 Implemented
SF0157 # 02 Y:1999 02 1999 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $18,418 $45,400 Implemented
SF0157 # 03 Y:1999 03 1999 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $396 $2,106 Implemented
SF0157 # 04 Y:1999 04 1999 INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE $3,602 $0 Not Implemented
SF0157 # 05 Y:1999 05 1999 CONTRACT A WOOD PALLET RECYCLING COMPANY $960 $250 Implemented
SF0157 # 06 Y:1999 06 1999 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER $19,132 $49,350 Not Implemented
SF0157 # 07 Y:1999 07 1999 ADOPT IN-HOUSE MATERIAL GENERATION $78,960 $30,000 Not Implemented
UF0211 # 01 Y:1998 01 1998 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,004 $7,226 Implemented
UF0211 # 02 Y:1998 02 1998 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,672 $1,458 Implemented
UF0211 # 03 Y:1998 03 1998 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $12,742 $3,800 Implemented
UF0211 # 04 Y:1998 04 1998 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,779 $0 Implemented
UF0211 # 05 Y:1998 05 1998 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $2,297 $750 Implemented
UF0211 # 06 Y:1998 06 1998 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $1,188 $642 Not Implemented
UF0211 # 07 Y:1998 07 1998 OPTIMIZE PLANT POWER FACTOR $1,623 $5,000 Not Implemented
UF0211 # 08 Y:1998 08 1998 USE WASTE HEAT STEAM FOR ABSORPTION REFRIGERATION $14,651 $28,996 Not Implemented
UF0211 # 09 Y:1998 09 1998 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) $1,843 $1,500 Not Implemented
UF0211 # 10 Y:1998 10 1998 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $2,727 $0 Implemented
UF0211 # 11 Y:1998 11 1998 PURCHASE EQUIPMENT INSTEAD OF LEASING $39,900 $123,000 Implemented
UF0211 # 12 Y:1998 12 1998 APPLY FOR INVESTMENT INCENTIVES $36,605 $50 Not Implemented
UF0211 # 13 Y:1998 13 1998 MODIFY STORAGE SPACE TO AVOID RENTAL OF A WAREHOUSE $172,000 $150,000 Implemented
NC0145 # 01 Y:1998 01 1998 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING $5,611 $25,000 Not Implemented