Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,301
matching recommendationsSIC | 275 | Commercial Printing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NL0046 # 05 Y:2020 | 05 | 2020 | CONDENSE OPERATION INTO ONE BUILDING | $2,848 | $9,480 | Implemented |
NL0046 # 06 Y:2020 | 06 | 2020 | MAINTAIN AIR FILTERS BY CLEANING OR REPLACEMENT | $495 | $44 | Implemented |
NL0046 # 07 Y:2020 | 07 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $425 | $2,064 | Implemented |
NL0046 # 08 Y:2020 | 08 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $288 | $1,600 | Implemented |
NL0046 # 09 Y:2020 | 09 | 2020 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $220 | $525 | Implemented |
NL0046 # 10 Y:2020 | 10 | 2020 | INSTALL OCCUPANCY SENSORS | $98 | $298 | Implemented |
WM0148 # 01 Y:2019 | 01 | 2019 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $23,863 | $21,000 | Not Implemented |
WM0148 # 02 Y:2019 | 02 | 2019 | USE SOLAR HEAT TO MAKE ELECTRICTY | $21,662 | $106,000 | Not Implemented |
WM0148 # 03 Y:2019 | 03 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,757 | $0 | Not Implemented |
WM0148 # 04 Y:2019 | 04 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,118 | $5,000 | Implemented |
WM0148 # 05 Y:2019 | 05 | 2019 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,478 | $8,880 | Not Implemented |
WM0148 # 06 Y:2019 | 06 | 2019 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $3,158 | $1,365 | Implemented |
WM0148 # 07 Y:2019 | 07 | 2019 | USE RADIANT HEATER FOR SPOT HEATING | $3,041 | $2,800 | Not Implemented |
WM0148 # 08 Y:2019 | 08 | 2019 | INSTALL OCCUPANCY SENSORS | $1,718 | $2,325 | Not Implemented |
WM0148 # 09 Y:2019 | 09 | 2019 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,616 | $3,900 | Not Implemented |
WM0148 # 10 Y:2019 | 10 | 2019 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $1,409 | $1,750 | Not Implemented |
WM0148 # 11 Y:2019 | 11 | 2019 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $1,396 | $0 | Implemented |
WM0148 # 12 Y:2019 | 12 | 2019 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,320 | $2,340 | Not Implemented |
WM0148 # 13 Y:2019 | 13 | 2019 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $1,087 | $0 | Not Implemented |
WM0148 # 14 Y:2019 | 14 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $805 | $1,664 | Implemented |
WM0148 # 15 Y:2019 | 15 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $741 | $970 | Not Implemented |
WM0148 # 16 Y:2019 | 16 | 2019 | AVOID INTRODUCING HOT, HUMID, OR DIRTY AIR INTO HVAC SYSTEM | $617 | $1,175 | Not Implemented |
UK1910 # 01 Y:2019 | 01 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $7,415 | $2,477 | Implemented |
UK1910 # 02 Y:2019 | 02 | 2019 | AVOID INTRODUCING HOT, HUMID, OR DIRTY AIR INTO HVAC SYSTEM | $510 | $1,775 | Implemented |
UK1910 # 03 Y:2019 | 03 | 2019 | INSULATE BARE EQUIPMENT | $280 | $161 | Implemented |