Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
70
matching recommendationsSIC | 2752 | Commercial Printing, Lithographic |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SD0634 # 01 Y:2023 | 01 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $942 | $3,568 | Implemented |
SD0634 # 04 Y:2023 | 04 | 2023 | USE PROPERLY DESIGNED AND SIZED HVAC EQUIPMENT | $4,998 | $15,050 | Implemented |
SD0634 # 03 Y:2023 | 03 | 2023 | AVOID INTRODUCING HOT, HUMID, OR DIRTY AIR INTO HVAC SYSTEM | $2,222 | $2,580 | Implemented |
SD0634 # 02 Y:2023 | 02 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,518 | $700 | Implemented |
SD0634 # 05 Y:2023 | 05 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $49,771 | $108,198 | Implemented |
SD0634 # 07 Y:2023 | 07 | 2023 | UPGRADE CONTROLS ON COMPRESSORS | $585 | $250 | Implemented |
SD0634 # 06 Y:2023 | 06 | 2023 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $15,780 | $11,100 | Implemented |
SF0587 # 04 Y:2022 | 04 | 2022 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $34,250 | $35,738 | Implemented |
SF0587 # 05 Y:2022 | 05 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,067 | $1,675 | Implemented |
SF0587 # 06 Y:2022 | 06 | 2022 | USE SOLAR HEAT TO MAKE ELECTRICTY | $12,549 | $55,774 | Implemented |
SF0587 # 03 Y:2022 | 03 | 2022 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $9,849 | $3,482 | Implemented |
SF0587 # 01 Y:2022 | 01 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,467 | $0 | Implemented |
SF0587 # 02 Y:2022 | 02 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,769 | $260 | Implemented |
SD0582 # 03 Y:2019 | 03 | 2019 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $4,534 | $9,736 | Implemented |
SD0582 # 04 Y:2019 | 04 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $342 | $760 | Implemented |
SD0582 # 02 Y:2019 | 02 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,455 | $8,348 | Implemented |
SD0582 # 01 Y:2019 | 01 | 2019 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $24,520 | $35,000 | Implemented |
SF0540 # 01 Y:2019 | 01 | 2019 | USE DRYING OVEN (BATCH TYPE) ON ALTERNATE DAYS OR OTHER OPTIMUM SCHEDULE TO RUN EQUIPMENT WITH FULL LOADS | $3,623 | $0 | Implemented |
SF0540 # 06 Y:2019 | 06 | 2019 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,740 | $21,083 | Implemented |
SF0540 # 03 Y:2019 | 03 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,339 | $325 | Implemented |
SF0540 # 04 Y:2019 | 04 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,918 | $19,682 | Implemented |
SF0540 # 05 Y:2019 | 05 | 2019 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $242 | $688 | Implemented |
SF0540 # 02 Y:2019 | 02 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,827 | $0 | Implemented |
SD0534 # 08 Y:2016 | 08 | 2016 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $357 | $200 | Implemented |
SD0534 # 02 Y:2016 | 02 | 2016 | AVOID INTRODUCING HOT, HUMID, OR DIRTY AIR INTO HVAC SYSTEM | $12,021 | $5,775 | Implemented |