Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,905
matching recommendationsSIC | 2752 | Commercial Printing, Lithographic |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CL1906 # 01 Y:2019 | 01 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,464 | $12,357 | Implemented |
CL1906 # 02 Y:2019 | 02 | 2019 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $694 | $0 | Implemented |
CL1906 # 03 Y:2019 | 03 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,979 | $1,440 | Implemented |
CL1906 # 04 Y:2019 | 04 | 2019 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $816 | $574 | Implemented |
LE0469 # 01 Y:2019 | 01 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,507 | $1,000 | Not Implemented |
LE0469 # 02 Y:2019 | 02 | 2019 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $159 | $175 | Not Implemented |
LE0469 # 03 Y:2019 | 03 | 2019 | RECOVER WASTE HEAT FROM EQUIPMENT | $5,321 | $6,000 | Not Implemented |
LE0469 # 04 Y:2019 | 04 | 2019 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $18,723 | $23,000 | Not Implemented |
LE0469 # 05 Y:2019 | 05 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,425 | $18,125 | Not Implemented |
UF0522 # 01 Y:2018 | 01 | 2018 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $36,742 | $240,000 | Not Implemented |
UF0522 # 02 Y:2018 | 02 | 2018 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $87,600 | $7,358 | Not Implemented |
UF0522 # 03 Y:2018 | 03 | 2018 | RECOVER WASTE HEAT FROM EQUIPMENT | $21,070 | $48,000 | Not Implemented |
UF0522 # 04 Y:2018 | 04 | 2018 | TURN OFF EQUIPMENT WHEN NOT IN USE | $10,267 | $0 | Implemented |
UF0522 # 05 Y:2018 | 05 | 2018 | INSTALL SKYLIGHTS | $9,473 | $48,000 | Not Implemented |
UF0522 # 06 Y:2018 | 06 | 2018 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $5,837 | $0 | Implemented |
UF0522 # 07 Y:2018 | 07 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,481 | $1,413 | Implemented |
UF0522 # 08 Y:2018 | 08 | 2018 | INSTALL OCCUPANCY SENSORS | $4,644 | $797 | Implemented |
UF0522 # 09 Y:2018 | 09 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,753 | $688 | Implemented |
UF0522 # 10 Y:2018 | 10 | 2018 | REPLACE OLD MACHINE WITH NEW AUTOMATIC MULTI-STATION TOOL | $60,514 | $190,580 | Not Implemented |
UF0519 # 01 Y:2018 | 01 | 2018 | USE PROPERLY DESIGNED AND SIZED HVAC EQUIPMENT | $27,363 | $868 | Implemented |
UF0519 # 02 Y:2018 | 02 | 2018 | OPTIMIZE PLANT POWER FACTOR | $17,618 | $30,000 | Not Implemented |
UF0519 # 03 Y:2018 | 03 | 2018 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $11,657 | $25,600 | Not Implemented |
UF0519 # 04 Y:2018 | 04 | 2018 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $8,569 | $45,225 | Implemented |
UF0519 # 05 Y:2018 | 05 | 2018 | ISOLATE HOT OR COLD EQUIPMENT | $6,694 | $2,710 | Not Implemented |
UF0519 # 06 Y:2018 | 06 | 2018 | UPGRADE CONTROLS ON COMPRESSORS | $5,422 | $25,600 | Not Implemented |