Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,905
matching recommendationsSIC | 2752 | Commercial Printing, Lithographic |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CO0091 # 05 Y:1987 | 05 | 1987 | IMPROVE LUBRICATION PRACTICES | $608 | $0 | Implemented |
CO0091 # 06 Y:1987 | 06 | 1987 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $399 | $676 | Implemented |
CO0091 # 07 Y:1987 | 07 | 1987 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,261 | $1,500 | Implemented |
CO0091 # 08 Y:1987 | 08 | 1987 | INSTALL TIMERS AND/OR THERMOSTATS | $22,175 | $1,682 | Implemented |
CO0091 # 09 Y:1987 | 09 | 1987 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,091 | $2,000 | Implemented |
GT0310 # 01 Y:1987 | 01 | 1987 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,060 | $300 | Not Implemented |
GT0310 # 02 Y:1987 | 02 | 1987 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $7,080 | $2,000 | Not Implemented |
GT0310 # 03 Y:1987 | 03 | 1987 | INSULATE BARE EQUIPMENT | $220 | $140 | Not Implemented |
GT0310 # 04 Y:1987 | 04 | 1987 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $4,325 | $2,375 | Not Implemented |
GT0310 # 05 Y:1987 | 05 | 1987 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $582 | $2,216 | Not Implemented |
GT0310 # 06 Y:1987 | 06 | 1987 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $18,930 | $41,000 | Not Implemented |
MA0082 # 01 Y:1987 | 01 | 1987 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,617 | $340 | Not Implemented |
MA0082 # 02 Y:1987 | 02 | 1987 | BURN A LESS EXPENSIVE GRADE OF FUEL | $2,485 | $0 | Implemented |
MA0082 # 03 Y:1987 | 03 | 1987 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $2,118 | $1,875 | Implemented |
MA0082 # 04 Y:1987 | 04 | 1987 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $14,872 | $300 | Implemented |
MA0082 # 05 Y:1987 | 05 | 1987 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $11,848 | $890 | Implemented |
MA0082 # 06 Y:1987 | 06 | 1987 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $4,708 | $7,608 | Implemented |
KU0182 # 01 Y:1986 | 01 | 1986 | USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT | $109,167 | $1,000,000 | Not Implemented |
KU0182 # 02 Y:1986 | 02 | 1986 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,883 | $10,000 | Implemented |
KU0182 # 03 Y:1986 | 03 | 1986 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,269 | $20 | Not Implemented |
KU0182 # 04 Y:1986 | 04 | 1986 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $418 | $700 | Implemented |
KU0182 # 05 Y:1986 | 05 | 1986 | INSTALL AUTOMATIC STACK DAMPER | $3,144 | $3,000 | Implemented |
KU0182 # 06 Y:1986 | 06 | 1986 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $882 | $2,000 | Implemented |
KU0182 # 07 Y:1986 | 07 | 1986 | USE WASTE HEAT FROM HOT FLUE GASES TO GENERATE STEAM | $801 | $1,400 | Not Implemented |
KU0182 # 08 Y:1986 | 08 | 1986 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $160 | $0 | Implemented |