Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
86
matching recommendationsSIC | 2759 | Commercial Printing, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0223 # 01 Y:1987 | 01 | 1987 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,228 | $2,950 | Implemented |
KU0131 # 04 Y:1984 | 04 | 1984 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $4,270 | $235 | Not Implemented |
KU0131 # 05 Y:1984 | 05 | 1984 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,310 | $170 | Implemented |
KU0131 # 06 Y:1984 | 06 | 1984 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,902 | $30 | Not Implemented |
KU0131 # 07 Y:1984 | 07 | 1984 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $485 | $350 | Implemented |
KU0131 # 08 Y:1984 | 08 | 1984 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $975 | $1,000 | Not Implemented |
KU0131 # 09 Y:1984 | 09 | 1984 | INSTALL AUTOMATIC STACK DAMPER | $897 | $2,000 | Not Implemented |
KU0131 # 10 Y:1984 | 10 | 1984 | INSTALL TURBULATORS | $289 | $650 | Not Implemented |
KU0131 # 11 Y:1984 | 11 | 1984 | MINIMIZE BOILER BLOWDOWN WITH BETTER FEEDWATER TREATMENT | $162 | $0 | Not Implemented |
KU0131 # 12 Y:1984 | 12 | 1984 | MINIMIZE BOILER BLOWDOWN WITH BETTER FEEDWATER TREATMENT | $109 | $0 | Not Implemented |
KU0131 # 13 Y:1984 | 13 | 1984 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $396 | $0 | Implemented |
KU0131 # 14 Y:1984 | 14 | 1984 | ESTABLISH EQUIPMENT MAINTENANCE SCHEDULE | $330 | $0 | Implemented |
KU0131 # 15 Y:1984 | 15 | 1984 | INSTALL AUTOMATIC STACK DAMPER | $461 | $800 | Not Implemented |
KU0131 # 16 Y:1984 | 16 | 1984 | SHUT OFF PILOTS IN STANDBY EQUIPMENT | $136 | $0 | Implemented |
KU0131 # 17 Y:1984 | 17 | 1984 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $147 | $0 | Not Implemented |
KU0131 # 18 Y:1984 | 18 | 1984 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $127 | $63 | Not Implemented |
KU0131 # 19 Y:1984 | 19 | 1984 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $113 | $39 | Implemented |
KU0131 # 03 Y:1984 | 03 | 1984 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,281 | $200 | Implemented |
KU0131 # 02 Y:1984 | 02 | 1984 | MINIMIZE USE OF OUTSIDE MAKE-UP AIR FOR VENTILATION EXCEPT WHEN USED FOR ECONOMIZER CYCLE | $8,554 | $18,500 | Not Implemented |
KU0131 # 01 Y:1984 | 01 | 1984 | USE WASTE HEAT FROM HOT FLUE GASES TO GENERATE STEAM | $15,513 | $17,900 | Not Implemented |
KU0120 # 02 Y:1984 | 02 | 1984 | USE ONLY AMOUNT OF AIR NECESSARY TO PREVENT EXPLOSION HAZARD | $2,048 | $200 | Not Implemented |
KU0120 # 01 Y:1984 | 01 | 1984 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,272 | $2,159 | Implemented |
KU0120 # 03 Y:1984 | 03 | 1984 | IMPROVE LUBRICATION PRACTICES | $1,536 | $215 | Not Implemented |
KU0120 # 04 Y:1984 | 04 | 1984 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $917 | $0 | Implemented |
KU0120 # 05 Y:1984 | 05 | 1984 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,077 | $70 | Implemented |