Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
8,892
matching recommendationsSIC | 28 | Chemicals And Allied Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD0186 # 03 Y:1986 | 03 | 1986 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $23,369 | $26,000 | Implemented |
AT0032 # 04 Y:1985 | 04 | 1985 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,049 | $825 | Implemented |
AT0032 # 05 Y:1985 | 05 | 1985 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,312 | $465 | Implemented |
AT0032 # 06 Y:1985 | 06 | 1985 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $859 | $720 | Implemented |
AT0032 # 07 Y:1985 | 07 | 1985 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $6,603 | $2,700 | Implemented |
AT0032 # 08 Y:1985 | 08 | 1985 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $304 | $400 | Implemented |
AT0032 # 01 Y:1985 | 01 | 1985 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,538 | $3,544 | Implemented |
AT0032 # 02 Y:1985 | 02 | 1985 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,391 | $300 | Implemented |
AT0032 # 03 Y:1985 | 03 | 1985 | INSTALL / REPAIR INSULATION ON STEAM LINES | $8,375 | $3,000 | Implemented |
MA0041 # 01 Y:1985 | 01 | 1985 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,442 | $2,640 | Implemented |
MA0041 # 02 Y:1985 | 02 | 1985 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $7,972 | $9,826 | Implemented |
MA0041 # 03 Y:1985 | 03 | 1985 | AIR CONDITION ONLY SPACE NECESSARY | $16,180 | $17,180 | Not Implemented |
MA0041 # 04 Y:1985 | 04 | 1985 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $192 | $143 | Implemented |
KU0175 # 01 Y:1985 | 01 | 1985 | INSTALL TIMERS AND/OR THERMOSTATS | $1,551 | $484 | Implemented |
KU0175 # 02 Y:1985 | 02 | 1985 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,405 | $2,503 | Implemented |
KU0175 # 03 Y:1985 | 03 | 1985 | USE ONLY AMOUNT OF AIR NECESSARY TO PREVENT EXPLOSION HAZARD | $875 | $22 | Implemented |
KU0175 # 04 Y:1985 | 04 | 1985 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $576 | $0 | Implemented |
KU0175 # 05 Y:1985 | 05 | 1985 | INSTALL AUTOMATIC STACK DAMPER | $414 | $1,300 | Not Implemented |
KU0175 # 06 Y:1985 | 06 | 1985 | SHUT OFF PILOTS IN STANDBY EQUIPMENT | $337 | $0 | Implemented |
KU0175 # 07 Y:1985 | 07 | 1985 | USE FLUE GASES IN RADIANT HEATER FOR SPACE HEATING, OVENS, ETC | $313 | $1,500 | Not Implemented |
KU0175 # 08 Y:1985 | 08 | 1985 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $191 | $0 | Implemented |
KU0175 # 09 Y:1985 | 09 | 1985 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $175 | $0 | Implemented |
AT0028 # 01 Y:1985 | 01 | 1985 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $591 | $818 | Implemented |
AT0028 # 02 Y:1985 | 02 | 1985 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,845 | $361 | Implemented |
AT0028 # 03 Y:1985 | 03 | 1985 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $825 | $0 | Implemented |