IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

43

matching recommendations
Reset
SIC 2821 Plastics Materials And Resins
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
AM0781 # 05 Y:2019 05 2019 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $445 $780 Implemented
AM0781 # 04 Y:2019 04 2019 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $805 $762 Not Implemented
AM0781 # 03 Y:2019 03 2019 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,710 $7,720 Implemented
AM0781 # 02 Y:2019 02 2019 OPTIMIZE PLANT POWER FACTOR $6,054 $17,860 Not Implemented
AM0781 # 01 Y:2019 01 2019 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $4,349 $43 Not Implemented
AM0718 # 04 Y:2016 04 2016 USE SYNTHETIC LUBRICANT $28,832 $0 Implemented
AM0718 # 05 Y:2016 05 2016 INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS $10,555 $1,800 Not Implemented
AM0718 # 03 Y:2016 03 2016 USE STEAM PRESSURE REDUCTION TO GENERATE POWER $65,900 $400,000 Not Implemented
AM0718 # 01 Y:2016 01 2016 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $123,800 $195,000 Not Implemented
AM0718 # 02 Y:2016 02 2016 OPTIMIZE PLANT POWER FACTOR $53,431 $280,072 Not Implemented
AM0587 # 02 Y:2010 02 2010 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $7,460 $21,600 Implemented
AM0587 # 06 Y:2010 06 2010 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $3,250 $500 Implemented
AM0587 # 01 Y:2010 01 2010 REPAIR AND ELIMINATE STEAM LEAKS $8,000 $5,000 Implemented
AM0587 # 03 Y:2010 03 2010 INSTALL / REPAIR INSULATION ON STEAM LINES $5,760 $1,030 Implemented
AM0587 # 04 Y:2010 04 2010 OPTIMIZE PLANT POWER FACTOR $5,087 $21,130 Not Implemented
AM0587 # 08 Y:2010 08 2010 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED $1,521 $560 Implemented
AM0587 # 05 Y:2010 05 2010 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $4,760 $42 Not Implemented
AM0587 # 07 Y:2010 07 2010 INSTALL SKYLIGHTS $2,550 $2,030 Not Implemented
AM0587 # 09 Y:2010 09 2010 USE SYNTHETIC LUBRICANT $980 $0 Not Implemented
AM0475 # 02 Y:2004 02 2004 REPAIR AND ELIMINATE STEAM LEAKS $5,800 $700 Implemented
AM0475 # 03 Y:2004 03 2004 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $5,390 $500 Implemented
AM0475 # 01 Y:2004 01 2004 REPAIR OR REPLACE STEAM TRAPS $19,000 $650 Implemented
AM0475 # 09 Y:2004 09 2004 INSTALL / REPAIR INSULATION ON CONDENSATE LINES $1,600 $12,500 Not Implemented
AM0475 # 10 Y:2004 10 2004 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT $1,740 $425 Implemented
AM0475 # 11 Y:2004 11 2004 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL $572 $699 Not Implemented